Term
What master data is relevant for material planning? (3 answers) |
|
Definition
- material - bill of material - routings |
|
|
Term
The MRP views of the material master are relevant at what organizational level? (1 answer) |
|
Definition
|
|
Term
The Accounting views of the material master are relevant at what organizational level? (1 answer) |
|
Definition
|
|
Term
The material type of a material determines what? (5 answers) |
|
Definition
- Default procurement type - Material number - Material views available - Relevant general ledger accounts - Business processes and functions allowed |
|
|
Term
What are valid procurement types? (3 answers) |
|
Definition
- external - interanl - external and internal |
|
|
Term
What are potential MRP types? (3 answers) |
|
Definition
- MRP - Consumption based - No planning |
|
|
Term
What are item categories in BOMs? (4 answers) |
|
Definition
- Stock - Non-stock - Variable-size - Document |
|
|
Term
Steps in the material planning process? (5 answers) |
|
Definition
- CO-PA - SOP - MPS - MRP - Demand Management |
|
|
Term
Ways to create sales plans in SOP? (4 answers) |
|
Definition
- Forecast using historical data from SIS - Sales plan from CO-PA - Copy from another production group - Manually |
|
|
Term
True statements about consumption-based planning? (3 answers) |
|
Definition
- Is based on historical rates of consumption - Is appropriate for low value materials - Procurement is triggered when stocks fall below the reorder point |
|
|
Term
For externally procured materials MRP can produce: (3 answers) |
|
Definition
- Planned orders - Purchase requisition - Schedule lines |
|
|
Term
Basic data in the material master is applicable to the entire company, but is stored at the plant level. (True/False) |
|
Definition
|
|
Term
Routings can be transferred to APO in the form of: (1 answer) |
|
Definition
|
|
Term
The first step in material planning is: (1 answer) |
|
Definition
|
|
Term
Time periods in the standard planning table could be: (CATA - 4 answers) |
|
Definition
- days - weeks - accounting periods - sales periods |
|
|
Term
In material planning, sales orders consume independent requirements. The consumption mode and consumption periods can be set in: (2 answers) |
|
Definition
- Material master - MRP group |
|
|
Term
Consumption based planning can be done on what levels? (3 answers) |
|
Definition
- Reorder-point planning - Forecast-based planning - Time-phased planning |
|
|
Term
MRP Control Parameters include: (5 answers) |
|
Definition
- Processing keys - Create Purchase Requisitions - Schedule lines - Create MRP list - Planning mode |
|
|