Term
Function of reactor pressure relief |
|
Definition
Provide primary system overpressure protection. Provide automatic and manual RPV depressurization or pressure control. Flow path for alternate shutdown cooling.
|
|
|
Term
SRV design characteristics |
|
Definition
|
|
Term
ADS design characteristics |
|
Definition
Backup to HPCI. Enables low pressure ECCS to inject should HPCI fail to operate. |
|
|
Term
Lo Lo set design characteristics |
|
Definition
Minimizes SRV re-opening with discharge piping gilled with water |
|
|
Term
How does ADS/Lo-lo set actuate? |
|
Definition
|
|
Term
Minimum steam pressure that an SRV will remain open |
|
Definition
Below 50 psig, valves are not expected to remain open. |
|
|
Term
Bellows alarm setpoint and purpose |
|
Definition
|
|
Term
Valve leak detection alarm setpoint |
|
Definition
|
|
Term
Which of the reactor pressure relief systems are ECCS? |
|
Definition
|
|
Term
Requirements for ADS initiation |
|
Definition
107 sec Timer expiration Timer starts when: -47 inches reactor level AND AC interlock satisfied. NOTE: if low low level clears before timer expiration, then ADS does not initiate. However, if ADS initiates, then the only two things that will interrupt the signal are: |
|
|
Term
When does the ADS timer reset? |
|
Definition
If water level goes above -47 inches (with AC interlock prior to timer timing out), AC interlock not satisfied, Both INHIBIT switches
|
|
|
Term
|
Definition
|
|
Term
SRVs associated with Lo-Lo Set |
|
Definition
|
|
Term
Requirements for Lo-Lo set |
|
Definition
Full scram signal present Hand-switch in auto Reactor pressure below setpoint (1052, 1062, 1072 psig)
|
|
|
Term
|
Definition
H: 1052 psig G: 1062 psig E: 1072 psig Blowdown is approximately 80 psi |
|
|
Term
Time delay assoicated with Lo-Lo set |
|
Definition
10 seconds after valve shuts (Minimizes possibility of SRV re-opening with elevated water leg inside discharge piping.) |
|
|
Term
|
Definition
To provide backup to HPCI for automatic depressurization of the reactor vessel in time to permit LPCI and/or core spray systems to operate TO PREVENT FUEL CLAD MELTING DURING A SMALL BREAK LOSS OF COOLANT ACCIDENT. |
|
|
Term
How can ADS be interrupted? |
|
Definition
|
|
Term
|
Definition
MSIVs trip on: Less than 840 psig with mode switch in RUN Rx Low-Low Level (-47 inches) High Areal Temp (195-200 degrees F) 140% steam flow.
|
|
|
Term
|
Definition
PCT trips on: Rx Low Level (+9 inches) or High Drywell Pressure (1.84 psig)
|
|
|
Term
|
Definition
Non-liquid PCT trips on: Fuel pool high rad (50 mR/hr) or Rx Building Plenum High rad (26 mR/hr)
NOTE: these trips are NOT 1-out-of-2 taken twice. |
|
|
Term
|
Definition
RWCU trips on: Low-low leve (-47 inches) High drywell Pressure 1.84 psig High Flow (462 gpm for 10 seconds) Low Flow (-200 gpm for 10 seconds) RWCU room high temperature (170 degrees F)
|
|
|
Term
|
Definition
RCIC Isolates on: High steam flow (44,434 lbm/hr for 5 seconds) RCIC steam line area high temp (187.5 degrees F) RCIC steam line low pressure (60 psig)
|
|
|
Term
|
Definition
HPCI isolates on: High steam flow (300,000 lbm/hr for 4 seconds) Area temperature (187.5 degrees F) HPCI steam supply line low pressure (100 psig)
|
|
|
Term
PCIS Group I reset requirements |
|
Definition
Initiation signal must be clear All MSIV handswitches are placed in CLOSE Reset pushbutton
|
|
|
Term
PCIS Groups II and III reset requirements |
|
Definition
Initiation signal must be clear All handswitches in the group are placed in CLOSE with exception of MOVs Reset pushbuttons
|
|
|
Term
PCIS Groups IV and V reset requirements |
|
Definition
Initiating signals clear Reset Pushbuttons
|
|
|
Term
Low Low Set Division I power |
|
Definition
AC Source: Y10 DC Source: D33 |
|
|
Term
|
Definition
AC Source: B-44P DC Source: D100 |
|
|
Term
Pneumatic System Supply for SRVs |
|
Definition
Normal: Instrument Nitrogen
Safety-Related Backup: Alternate Nitrogen Train 'A': SRVs A, B, E Alternate Nitrogen Train 'B': SRV's C, H, F Accumulators: D and G
Nonsafety-Related Backup: Instrument Air |
|
|