Term
Two Methods of Root-Cause Analysis |
|
Definition
|
|
Term
|
Definition
To determine and analyze the Cause/s and Effect/s of each Risk: generally ONE effect at a time
Select risks considered significant based on Risk Register |
|
|
Term
what do you do with the identified Root Causes |
|
Definition
You create a plan of action to deal with them, or you record the analysis for lessons learned |
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
(Contingent Response) Planning – when done in advance best for unacceptable residual risks and for serious problems where all other approaches are too expensive, impractical, unknown, ... A Contingency Plan is Planned in advance of the occurrence of the risk event |
|
|
Term
|
Definition
to create a contingency for time or money |
|
|
Term
Contingency Plan - How/ Application |
|
Definition
Develop Recovery Plan Develop Fallback Plan (plan “B”) Assign Risk Owner Monitor Risk Trigger Respond Quickly Continual Sensible Evaluation: Progressive Elaboration |
|
|
Term
Contingency Application/ Action Plan |
|
Definition
-Who – Owner of the risk: person assigned to deal with it. -What –Specific actions/activities to achieve the Action Plan. -When – Target completion / deadline for the Action Plan activities. -How – resources (people, tools, equipment, money...) needed -Why – Eliminate/mitigate/transfer/Exploit, Accept… the risk |
|
|
Term
how can you use contractual agreement to respond to a risk |
|
Definition
Develop Risk Contractual Agreements --- examples
A Major Risk Transfer Strategy: Contracts – auto insurance, etc. Pay contractors to perform high-risk activities: experts! |
|
|
Term
RBS – what is it and where do you include it and why? |
|
Definition
RBS= a heirarchical representation of risks according to their risk categories, you use it during project planning and you can produce a go or no go from the results, and also determine which risks to create contingencies for and which risks just to monitor. |
|
|
Term
Workaround Vs Contingency |
|
Definition
Workaround: A response to a threat that has occurred, for which a prior response had not been planned or was not effective. Contingency: An event or occurrance that could affect the execution of the project that may be accounted for with a reserve |
|
|
Term
Project Level Risk v. Activity Level Risk |
|
Definition
Activity Risks – WBS-level (work package) risks: trench, nuts-&-bolts, micro-view Project Risks – Overall (holistic) project risks: looking at the entire project (macro-view), global view |
|
|
Term
Sources of Project Risks: See the Standish Report |
|
Definition
(a) Lack of User Involvement (b)Unrealistic Constraints. E.g. Top-Down estimates (c) Limited or Inaccurate Metrics Used for Estimates (d) Lack of Competent PMs (e) Inadequate Requirements: Scope Gap (f) Poor or Insufficient Change Management: Scope Creep (g) Oversized Projects (h) Poor or No Support / Sponsorship STANDISH REPORT: They are actually impossible, they are overconstrained (challenged); they are poorly managed |
|
|
Term
Aggregating Risk Responses |
|
Definition
Risk Responses are the planned actions to be taken to deal with risks. These actions need to be aggregated for combined result. -Assess and Prioritize all Project Risks. -Select the top (most severe) X risks. -Determine the required response for each risk. -Accumulate Consequences of Contingency Plans in Cost -and/or Schedule and Multiply by Probability. -Compare with PERT estimates minus the Most likely Activity Estimates (i.e.. te – tm; Ce-Cm). -Aggregate the responses to get total Contingency. NOTE: Aggregation of activity risks to obtain project risks is inaccurate due to non-consideration of the correlation between project risks. |
|
|
Term
Management Reserve Vs Contingency Reserve |
|
Definition
Contingency Reserve: Budget within a cost baseline or performance measurement baseline that is allocated for identified risks that are accepted and for which contingent or mitigating responses are developed.
Management Reserve: An amount of the project budget witheld for management control purposes. These are budgets reserved for unforeseen work that is within the scope of the project. THe management reserve is not included in the project measurement baseline. |
|
|
Term
Negotiating constraints: Fact Based negotiation |
|
Definition
Provide Definition & Planning Documents Provide High-level Objectives Summary, Milestones Project Schedule, High-level WBS, Project Appraisal, Summary of Major Risks & Assumptions, & other summary supporting documents based on WBS and Historical Information, Quotes,… Schedule Meeting w/Sponsor Present a Summary of Bottom-up Planning Results (WBS, etc) Negotiate Deviations from Original Requested Project Constraints (objectives) Request “Anything” and Provide Justification Present Data /Hard Facts /Studies /History Docs Know the Work, take SME, or Get Prep from SME. Negotiate…”Getting to Yes”…use win-win Concepts. Know your sponsor: should you ask for 50% more? Include all contingencies and reserves and be firm. Consider & Present Alternatives w/Pros and Cons using Bottom-up Plan Are the Objectives (Constraints) Realistic Consequences of Each Decision – effect/s on the other constraints Do not Accept Additional Unanalyzed Work |
|
|
Term
Result of Fact Based Negotiation |
|
Definition
Results of Negotiations Choose objectives at or Close to Planning Results Abandon the Project Based on Realistic Analysis of the Work and Risks Postpone decision to when compelling data is available-postponing decision may be due to on-the-spot Scope Change |
|
|
Term
If forced to take as demanded (rejection of fact based negotiation) |
|
Definition
Document Situation and Your Recommendations. Work Hard to Make it Happen or Look for Another Job. Remind the Sponsor of this Challenge: be constructive. Refuse to do the project --- PMBOK |
|
|
Term
Unknown Risks and Risks of lowest priority…what to do with them |
|
Definition
- create a management reserve - assign a team member to monitor the determined risk trigger for low priority risks |
|
|
Term
Analysis of Project Scale: what it is, its goal, what is used for |
|
Definition
Goal of this analysis: to weigh overall anticipated EFFORT in the project plan in order to: Classify each project on three levels of risk (low, normal, medium) based on its anticipated effort in comparison with earlier (previous) SUCCESSFUL (or failed) projects |
|
|
Term
Analysis of Project Scale: How is it done |
|
Definition
(1) Determine total EFFORT from Bottom-up project plan (e.g. WBS, schedule, cost, Quality,…) (2) Compare this scale with several, recent, similar projects (their efforts) Adjust data using staffing levels, project duration (schedule), overtime,… Calculate the Average (Mean) Determine the Risk level based on 3 Criteria: Low Risk if <60% Normal Risk if between 60% and 120% High Risk if >120% Adjust the Results: Raise the Risk Level to the next higher level if: Schedule is significantly compressed in the new project Project must use NEW technology 40% of the resources are either External or Unknown |
|
|
Term
Project Appraisal: what it is, its goal, what is used for |
|
Definition
Same principle used in interview-rating and in car, jewelry, home, art,…appraisal. Goal is to determine (calculate) the EFFORT required to get the project completed successfully. |
|
|
Term
Project Appraisal: How is it down |
|
Definition
Start with previously completed SUCCESSFUL (or failed) Project Evaluate and/or Convert Features to Effort-months, Effort-years, Effort-days, Effort-hours. Features used must be relevant to new project and must relate to Triple Constraints. Adjust Efforts up or down: based on available or missing feature/s. Find and use similar projects that mirror the new project as much as possible in order to only make minor adjustments in Effort value. (Adjustments: small differences: use +- 2 to 5%; Larger Differences: +- 7 to 10%) |
|
|
Term
Project Metrics: Predictive |
|
Definition
Predictive – use of current information to provide insight into future conditions. Least reliable – based on speculative data. (stock market). E.g. ROI Used for Early Warning Sign of Potential Project Risk Helps you anticipate problems: compare metrics with past success Can reveal enough correlations among various projects, helping the prediction of risks Not reliable: 80% of work is in 20% of time near project end |
|
|
Term
Use of Project Appraisal Results |
|
Definition
Determine if your Preliminary Plan is REALISTIC (the R in BARF): used for plan validation. If Appraised Value is Greater than Bottom-up Value by over 10%, find out WHY? New Project Efforts Estimate must be higher than average appraised value or Gap(s) exist(s) Provides early warning of possible budget over-run ***Risks accounted for in the new project from the old projects make Efforts in new Greater than Efforts in Old. These risks include UNKNOWS that became Known and were dealt with. These include Contingency plans and other risk recovery efforts. **Project Risk Management: helps achieve objectives Discussions with Sponsor for options, trade-offs, changes to over-constrained project: supports . |
|
|
Term
Project Metrics; Diagnostic |
|
Definition
assess state of ongoing process and may detect anomalies or forecast future problems EVM is an example of Diagnostic Metrics. EVM is used to determine whether the project is progressing as planned. Terms: EV(BCWP), AC(ACWP), PV(BCWS), CV, SV, CPI(=EV/AC), SPI(=EV/PV), BAC,…. |
|
|
Term
Project Metrics: Retrospective |
|
Definition
after the fact on HOW the process worked. Looks backward. Tracks trends. Validates Methods used for Predictive Metrics Identifies Recurring Sources of Risk Sets Standard for Reserves (schedule &/or Budget)…Management Reserves Determines Empirical Expectations for “Unknown” Project Risk Decides when to Improve or Replace Current Project Processes Output: Lessons Learned. |
|
|
Term
Project Metrics: Financial |
|
Definition
ROI – based on the Time-Value of Money. i.e. money today is worth more than the SAME quantity of money in the future. Interest rate and Time are main factors.
Payback Analysis (break-even time, payback period, ...)
NPV – net present value Another method to measure ROI Includes all the costs and all the anticipated benefits throughout the expected life of the project deliverable(s): determine costs and benefits separately over various points in time.
IRR – internal rate of return |
|
|
Term
Kick-off Meeting: definition and benefits |
|
Definition
Get-Acquainted Workshop/s: by conference; Best face-to-face WHY? Build Team Cohesion Introduce people & Rolls: Escalation & Updates Important especially for long projects Common project understanding at high level Key outputs: communications chain; escalation path;… |
|
|
Term
Management Reserve – Budget and Schedule. Use in reporting |
|
Definition
One help we need is Management Reserve Management Reserve: Time, Budget or BOTH are based on unexpected risk Required for credit budget and schedule. Project-level risk is used to define the size of the management reserve (a project-level item). ***Project objectives (constraints) are set with ranges determined by project-level risk assessment. |
|
|
Term
Schedule Reserve for Known Risks - based on Contingency |
|
Definition
Simplest Approach: -Determine Required Completion Date; e.g. 40 months -Determine Expected Schedule Reserve Risk Exposure; e.g. 10 months -Develop a Schedule to Finish Earlier; e.g. 30 months (“DUMMY Activity” = Allowance for Risk) = 10 months
B) Use PERT Values Tp and Tm: Schedule Reserve = Schedule Using Tp – Schedule Using Tm
Your Project will Use Tm to Manage the Project. If You Need the Reserve, Request it FORMALLY with Justification!!!
C)Use Data from Contingency Plans. Aggregate (accumulate) Activity Risk Effects on Schedule. Use Project Plans (WBS, Bottom-up,…) as Target Completion Date. Communicated Schedule Deadline is the date with Contingency Data (Risk Data) INCLUDED. Use the cumulative expected contingency of having to use the Contingency Plan. Communicated Deadline = (Risk) Schedule based on Contingency-Plan-Data Target Completion Date = Project-Plan-Based Schedule (WBS, Bottom-up,…)
(D) Schedule Reserve Amount for UNKNOWN Risks: PERT based on Previous “Unknown” Risks Typical to Type of Project Monte Carlo Simulations Histogram Expected Distributions Use Tm for early end date Use Tp for late end date based on Stakeholder Risk Tolerance |
|
|
Term
Budget Reserve for Known Risks- based on Contingency |
|
Definition
Part of Resource Reserve Determined and Set Using Resource Analysis & Risk Data Amount Estimated Similarly Like Schedule Reserve (i.e. from analysis of known risks using worst cases, contingency plant, or budget analysis) Estimate for UNKNOW Risks uses Metrics derived from Previous projects Strictly for Risks Easier to Manage than Schedule Reserve: time elapses compared to just asking for more money |
|
|
Term
How to guard against Parkinsons Law |
|
Definition
Set a window of time when project activity MUST be completed Apply Discipline to Achieve this Have other(s) Help You Enforce this: Accountability!!! Set up a REWARD: Appropriate and Commensurate Plan a Celebration for EACH Milestone Plan to Celebrate Unused Schedule Reserve at Project End PMO to Monitor Project Manager’s Use of Reserve: Accountability Regular Report Just like Budget |
|
|
Term
Change Request Management/Steps: to avoid Scope Creep |
|
Definition
Justify the Change (based on what information you have even if you DISAGREE): Help Make Their Case IF… Best if Requestor Submits the Change: justification and resultant denial may not look good for PM Estimate Benefits / Cost from the Change Determine Impact on Triple Constraints
Strive to PREVENT Change Unless: Compelling Has Credible Business Basis Cannot be Limited Cannot be Deferred to ANOTHER/Separate Project Communicate/Show Specific Resources and ACTION Required for the Change.
Analyze Impact: Triple Constraints, Subjective Consequences & Unquantifiable Impacts Rate Impact of the Change: small, medium, major….based on your company’s standard, e.g. if over 10%...major, etc. Update and present “Final” picture. |
|
|
Term
Why Monitor and Control a Project? |
|
Definition
(Similar to Driving a Car) Proactive capturing of project problems in their infancy (small and easily manageable) Anticipation of potential problems—avoid most of them, transfer some, accept as few as possible, mitigate,… Makes for effective response such as workaround: if you are alert and watchful... Allows time for additional planning/plan modification. Allows more efficient gathering of lessons learned. Good reference data for long duration risk management planning. Early warning signals are more noticeable. Good, reliable, understandable info: reduces stress and anxiety due to less speculation. Detailed status provides recovery info Factual info—minimizes excessive optimism or exaggerated info. Detailed status provides recovery info. Factual info—minimizes excessive optimism or exaggerated pessimism. Helps guard against reporting “safe so far”. |
|
|
Term
Metrics and Trend Analysis |
|
Definition
After collecting status look for problems by analyzing variances. Variance analysis involves comparing the status information collected with the project baseline plan to identify any differences.
Trend Analysis: Periodically determine status data trends. Early trend detection preferred. If adverse trend: Adjust project end date Increase budget Add resources Renegotiate contract(s) Modify project scope (deliverables); ETC. |
|
|
Term
|
Definition
Formal Acceptance, FInal Project Report (accomplishments), Contract and Document Closeout, Acknowledging Contributions, Celebration, Project Retrospective Analysis |
|
|
Term
Avoid Rejection of Deliverables: |
|
Definition
SCOPE VERIFICATION (define) / Formal Acceptance of Deliverables (Successful Projects) Nightmare to have deliverable rejected TO AVOID REJECTION OF DELIVERABLES: Validate Initial Specifications (BARF) Prudent Change Management (BARF) Define ALL Final Acceptance Criteria / Requirements (Scope Definitions & Planning) TO AVOID REJECTION OF DELIVERABLES contd.: Perform Testing & Acceptance Requirements (EARLY and Often). Pilot tests Frequent Communications with Approvers/Customers/Stakeholders: Updates Proof-of-Concept(s) – prototype, model, ... Scope-Verify Interim Results (for PMI, note that Scope Verification belongs to Closeout ONLY!!!) Sign-offs on SH Expectations and Expected Results. |
|
|