Term
Project Cost Management Processes: |
|
Definition
Plan Cost Estimate Costs Determine Budgets Control Costs |
|
|
Term
|
Definition
are revenues minus expenditures |
|
|
Term
|
Definition
is the ratio of revenues to profits |
|
|
Term
|
Definition
considers the total cost of ownership, or development plus support costs, for a project |
|
|
Term
|
Definition
determines the estimated annual costs and benefits for a project and the resulting annual cash flow |
|
|
Term
|
Definition
benefits are those costs or benefits that an organization can easily measure in dollars |
|
|
Term
Intangible costs or benefits |
|
Definition
costs or benefits that are difficult to measure in monetary terms |
|
|
Term
|
Definition
costs that can be directly related to producing the products and services of the project |
|
|
Term
|
Definition
costs that are not directly related to the products or services of the project, but are indirectly related to performing the project |
|
|
Term
|
Definition
is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs in a budget |
|
|
Term
|
Definition
Cost estimates are influenced by many factors including labor rates, materials cost, economic factors, risk factors, etc. Expert judgment provides insights into evaluation of these factors into cost estimation. |
|
|
Term
|
Definition
Using values such as scope, cost estimates, time estimates, complexity from similar projects. Use actual costs from prior project and adjust for known differences. This is a part of cost estimation. |
|
|
Term
|
Definition
Uses statistical techniques to predict from historical data. Can produce higher levels of estimates depending on the sophistication of the statistical techniques. |
|
|
Term
|
Definition
Uses WBS to estimate each component of work. The costs of each work package is the rolled up into subtotals for tasks. |
|
|
Term
|
Definition
Contingency reserves (contingency allowances). Can be percentage of estimated cost, an actual $ figure or determined through parametric analysis |
|
|
Term
Rough order of magnitude (ROM) |
|
Definition
Accuracy ranges from -25% to +75% (just know large range). Usually used in initiation process to establish high-level budget. |
|
|
Term
|
Definition
Accuracy ranges from -10% to +25% (just know medium range). Usually used in planning process to establish early budget estimates. Also used in top-down estimating (Using prior project to estimate project costs) |
|
|
Term
|
Definition
Accuracy ranges from -5% to + 10% (just know small range). Usually used late in planning phase and in bottom-up estimating (use of WBS) |
|
|
Term
Earned Value Management (EVM) |
|
Definition
- Method of performance measurement. It integrates project scope, costs and schedule to help project team assess status, performance and progress. EVM monitors 3 key dimensions: -Planned Value -Earned Value - Actual Cost This is a part of "Control Costs" |
|
|
Term
|
Definition
formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period |
|
|
Term
|
Definition
formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period |
|
|
Term
|
Definition
formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed |
|
|
Term
|
Definition
All start wit hEV -V =EV-AC - SV=EV -PV - CPI=EV / AC - SPI=EV/PV Variance means subtract Index means divide Less than 1 is bad in an index Negative is bad in a variance |
|
|
Term
|
Definition
Cost variance is the difference between the earned value and the actual cost. CV = EV -AC |
|
|
Term
|
Definition
Schedule variance is the difference between the earned value and the planned value. SV = EV -PV |
|
|
Term
Cost Performance Index (CPI) |
|
Definition
Cost performance index is the amount of work the project is completing per dollar spent on the project. CPI= EV /AC |
|
|
Term
Schedule Performance Index (SPI) |
|
Definition
Cost performance index reveals how close the project is to being on schedule. SPI= EV /PV |
|
|
Term
Estimate to Complete(ETC) |
|
Definition
Estimate to completion is a “best guess” as to how much money it will take to complete the project. |
|
|
Term
Estimate at Completion(EAC) |
|
Definition
Estimate at completion is a “best guess” as to what the total cost of the project will be based on the experiences with the project so far. |
|
|
Term
Control Cost Cause of Variation |
|
Definition
- Things beyond our control (force majeure) - Bad planning - Poorly designed contracts - Unrealistic cost estimates - Unrealistic time estimates - Changes in technology - Changes in regulations - Laissez-faire project management - Poor risk management |
|
|
Term
To Complete Performance Index |
|
Definition
is a forecast of cost performance that must be attained on remaining work in order to meet a specified management goal or goals. This is a part of cost control |
|
|