Shared Flashcard Set

Details

Test 4: Project Cost Management
PM
31
Health Care
Graduate
06/21/2017

Additional Health Care Flashcards

 


 

Cards

Term
Project Cost Management Processes:
Definition
Plan Cost
Estimate Costs
Determine Budgets
Control Costs
Term
Profits
Definition
are revenues minus expenditures
Term
Profit margin
Definition
is the ratio of revenues to profits
Term
Life cycle costing
Definition
considers the total cost of ownership, or development plus support costs, for a project
Term
Cash flow analysis
Definition
determines the estimated annual costs and benefits for a project and the resulting annual cash flow
Term
Tangible costs or
Definition
benefits are those costs or benefits that an organization can easily measure in dollars
Term
Intangible costs or benefits
Definition
costs or benefits that are difficult to measure in monetary terms
Term
Direct costs
Definition
costs that can be directly related to producing the products and services of the project
Term
Indirect costs
Definition
costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
Term
Sunk cost
Definition
is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs in a budget
Term
Expert Judgment
Definition
Cost estimates are influenced by many factors including labor rates, materials cost, economic factors, risk factors, etc. Expert judgment provides insights into evaluation of these factors into cost estimation.
Term
Analogous Estimating
Definition
Using values such as scope, cost estimates, time estimates, complexity from similar projects. Use actual costs from prior project and adjust for known differences. This is a part of cost estimation.
Term
Parametric Estimating
Definition
Uses statistical techniques to predict from historical data. Can produce higher levels of estimates depending on the sophistication of the statistical techniques.
Term
Bottom-up Estimating
Definition
Uses WBS to estimate each component of work. The costs of each work package is the rolled up into subtotals for tasks.
Term
Reserve analysis
Definition
Contingency reserves (contingency allowances). Can be percentage of estimated cost, an actual $ figure or determined through parametric analysis
Term
Rough order of magnitude (ROM)
Definition
Accuracy ranges from -25% to +75% (just know large range). Usually used in initiation process to establish high-level budget.
Term
Budget estimate
Definition
Accuracy ranges from -10% to +25% (just know medium range). Usually used in planning process to establish early budget estimates. Also used in top-down estimating (Using prior project to estimate project costs)
Term
Definitive estimates
Definition
Accuracy ranges from -5% to + 10% (just know small range). Usually used late in planning phase and in bottom-up estimating (use of WBS)
Term
Earned Value Management (EVM)
Definition
- Method of performance measurement. It integrates project scope, costs and schedule to help project team assess status, performance and progress. EVM monitors 3 key dimensions:
-Planned Value
-Earned Value
- Actual Cost
This is a part of "Control Costs"
Term
The planned value (PV)
Definition
formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
Term
Actual cost (AC)
Definition
formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
Term
The earned value (EV)
Definition
formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
Term
Control Cost Formulas
Definition
All start wit hEV
-V =EV-AC
- SV=EV -PV
- CPI=EV / AC
- SPI=EV/PV
Variance means subtract
Index means divide
Less than 1 is bad in an index
Negative is bad in a variance
Term
Cost Variance (CV)
Definition
Cost variance is the difference between the earned value and the actual cost.
CV = EV -AC
Term
Schedule Variance (SV)
Definition
Schedule variance is the difference between the earned value and the planned value.
SV = EV -PV
Term
Cost Performance Index (CPI)
Definition
Cost performance index is the amount of work the project is completing per dollar spent on the project.
CPI= EV /AC
Term
Schedule Performance Index (SPI)
Definition
Cost performance index reveals how close the project is to being on schedule.
SPI= EV /PV
Term
Estimate to Complete(ETC)
Definition
Estimate to completion is a “best guess” as to how much money it will take to complete the project.
Term
Estimate at Completion(EAC)
Definition
Estimate at completion is a “best guess” as to what the total cost of the project will be based on the experiences with the project so far.
Term
Control Cost Cause of Variation
Definition
- Things beyond our control (force majeure)
- Bad planning
- Poorly designed contracts
- Unrealistic cost estimates
- Unrealistic time estimates
- Changes in technology
- Changes in regulations
- Laissez-faire project management
- Poor risk management
Term
To Complete Performance Index
Definition
is a forecast of cost performance that must be attained on remaining work in order to meet a specified management goal or goals. This is a part of cost control
Supporting users have an ad free experience!