PMP study material
13
Computer Networking
Professional
05/23/2016

Additional Computer Networking Flashcards

 


 

Cards

Term
Present Value
Definition
PV = FV/(1+i)t
FV = future value, I = interest rate, t = time
Term
PERT
Definition
PERT = (P+4ML+O)/6
P = pessimistic, ML = Most likely, O = optimistic
Term
One Standard Deviation
Definition
1 Standard Deviation = |(P-O)/6|
P = pessimistic, O = optimistic
Term
Variance
Definition
Variance = (SD)2
SD = Standard Deviation
Term
Cost Variance (CV)
Definition
CV = EV-AC
EV = earned value, AC = actual cost
Term
Cost Performance Index (CPI)
Definition
CPI = EV/AC
EV = earned value, AC = actual cost
Term
Schedule Variance (SV)
Definition
SV = EV-PV
EV = earned value, PV = planned value
Term
Schedule Performance Index (SPI)
Definition
SPI = EV/PV
EV = earned value, PV = planned value
Term
Estimate at Completion (EAC)
assume we will continue spending at the same rate
Definition
EAC = BAC/CPI
BAC = budget at completion
CPI = cost performance index
Term
Estimate at Completion (ETC)
assume we will continue spending at the same rate
Definition
ETC = EAC-AC
EAC = estimate at completion
AC = actual cost
Term
Variance at Completion (VAC)
Definition
VAC = BAC-EAC
BAC = budget at completion
EAC = estimate at completion
Term
TCPI-using BAC

Total Cost Performance Index
Definition
TCPI = (BAC-EV)/(BAC-AC)
BAC = budget at completion
EV = earned value
AC = actual cost
Term
TCPI-using EAC

Total Cost Performance Index
Definition
TCPI = (BAC-EV)/(EAC-AC)
BAC = budget at completion
EV = earned value
EAC = estimate at completion
AC = actual cost