Term
|
Definition
PV = FV/(1+i)t FV = future value, I = interest rate, t = time |
|
|
Term
|
Definition
PERT = (P+4ML+O)/6 P = pessimistic, ML = Most likely, O = optimistic |
|
|
Term
|
Definition
1 Standard Deviation = |(P-O)/6| P = pessimistic, O = optimistic |
|
|
Term
|
Definition
Variance = (SD)2 SD = Standard Deviation |
|
|
Term
|
Definition
CV = EV-AC EV = earned value, AC = actual cost |
|
|
Term
Cost Performance Index (CPI) |
|
Definition
CPI = EV/AC EV = earned value, AC = actual cost |
|
|
Term
|
Definition
SV = EV-PV EV = earned value, PV = planned value |
|
|
Term
Schedule Performance Index (SPI) |
|
Definition
SPI = EV/PV EV = earned value, PV = planned value |
|
|
Term
Estimate at Completion (EAC) assume we will continue spending at the same rate |
|
Definition
EAC = BAC/CPI BAC = budget at completion CPI = cost performance index |
|
|
Term
Estimate at Completion (ETC) assume we will continue spending at the same rate |
|
Definition
ETC = EAC-AC EAC = estimate at completion AC = actual cost |
|
|
Term
Variance at Completion (VAC) |
|
Definition
VAC = BAC-EAC BAC = budget at completion EAC = estimate at completion |
|
|
Term
TCPI-using BAC
Total Cost Performance Index |
|
Definition
TCPI = (BAC-EV)/(BAC-AC) BAC = budget at completion EV = earned value AC = actual cost |
|
|
Term
TCPI-using EAC
Total Cost Performance Index |
|
Definition
TCPI = (BAC-EV)/(EAC-AC) BAC = budget at completion EV = earned value EAC = estimate at completion AC = actual cost |
|
|