Term
|
Definition
- Identifying the specific actions that must be performed to produce the project deliverables identified in the Work Breakdown Structure (WBS).
- Projct work packages are decomposed into smaller components called activities.
- Includes definition and planning of the activities such that project objectives will be met.
|
|
|
Term
|
Definition
-
A standard activity list or a portion of an activity list from a previous project which is used as a template for a new project.
-
The related attributes activity information can also contain other dexcriptive information useful in defining activities.
-
Can be used to identify schedule milestones.
|
|
|
Term
|
Definition
-
Is a comprehensive list of all schedule activities required on the project.
-
Includes the activity identifier and a scope of work definition for each activity in sufficient detail to ensure that the project team members understand what work need to be completed.
|
|
|
Term
|
Definition
-
Involves identifying and documenting interactivity logical relationships.
-
Activities must be sequenced accurately using lead and lag times to support later development of a realistic and achievable schedule.
-
Every activity and milestone except the first and the last should be connected to a predecessor and a successor activity.
|
|
|
Term
Mandatory Dependencies (or hard logic) |
|
Definition
|
|
Term
Discretionary Dependencies (preferred/soft logic) |
|
Definition
- Defined by the Project Management Team during Activity sequencing
- Referred to as preffered/preferential/soft logic
- based on best practices/ project speifics
- Should be fully documented as they can create arbitrary total float values
- to be reviewed when fast tracking techniques are employed
|
|
|
Term
|
Definition
-
Involve a relationship between project activities and non-project activities. (i.e. dependencies on issues which are beyond scope of the project)
-
Determined during activity sequencing by project team
-
Usually these are out of project team's control
|
|
|
Term
Precedence Diagramming Methods (PDM) |
|
Definition
-
Method used in CPM for constructing a project scedule network diagram that uses nodes to represent the activities and connects them with arrows that show the dependencies.
-
Also called as AON( activity on Node)
-
Contains four types of dependencies(FS,FF,SS,SF)
|
|
|
Term
|
Definition
|
|
Term
Project Network Diagrams/PERT Chart |
|
Definition
Schematic displays of project activities and logical relationships(dependencies) amongst them.
|
|
|
Term
Activity Duration Estimating |
|
Definition
Process of taking information on project scope and estimated resources and approximating work periods / durations for input to schedules. |
|
|
Term
Analogous Estimating (top-down) |
|
Definition
Using the actual duration of a previous similar activity as the basis for estimating the duration of a future activity. Used to estimate project duration when there is a limited amount of detailed information about the project. (e.g. in early phases) |
|
|
Term
Contingency, Buffer, Reserve |
|
Definition
The amount of funds, budget, or time needed above the estimate to reduce the risk of overruns of project objectives to a level acceptable to the organization. |
|
|
Term
Activity Duration Estimates |
|
Definition
Quantitative assessments of the likely number of work periods that will be required to complete an activity. |
|
|
Term
|
Definition
-
Determining start and finish dates for project activities and milestones.
-
If the start and finish dates are not realistic, then the project is unlikely to be finished as scheduled.
-
Schedule development can require the review and revision of duration estimates and resource estimates.
|
|
|
Term
Resource Pool Descriptions |
|
Definition
Knowledge of what resources will be available at what times and in what patterns - necessary for schedule development |
|
|
Term
|
Definition
- Project and Resource Calendars identify when the work is allowed.
- Resource Calendars - specify when and how long identified project resources will be available during the project.
- Project Calendar - a calaendar of working days or shiftsthat establishes those dates on whch schedule activities are worked , and also non working days,shifts on which schedule activities are idle. Typically defines, holdays, weekends and shift hours.
|
|
|
Term
|
Definition
A modification of a logical relationship that allows an acceleration of the successor activity. Successor Activity starts at a lead time before the predecessor activity has been completed.
E.g., in a Finish-to-Start dependancy, with a tenday lead, the successor activity can start ten days before the predecessor activity finishes. |
|
|
Term
|
Definition
Successor Activity starts only at a lag time after the predecessor activity has been completed i.e. there is a waiting time between completion of the first activity and beginning of the second activity |
|
|
Term
|
Definition
Involves calculating the theoretical early and late start and finish dates for all project activities without regard to any resource pool restrictions. |
|
|
Term
Critical Path Method (CPM) |
|
Definition
Calculates a single, deterministic early and late start start and finish date for each activity based on specified, sequential network logic |
|
|
Term
Graphical Review and Evaluation Technique (GERT) |
|
Definition
Allows for probabilistic treatment of both network logic and activity duration estimates |
|
|
Term
Program Review and Evaluation Technique (PERT) |
|
Definition
Uses a weighted average duration estimate to calculate activity durations - uses mean value(or expected value) of the distribution for calculations |
|
|
Term
|
Definition
Special case of mathematical analysis - looks to shorten the project schdule without changing the project scope. Includes techniques like crashing and fast tracking |
|
|
Term
|
Definition
Cost and schedule tradeoffs are analysed to determine how to get the greatest amount of compression for the least incremental cost. |
|
|
Term
|
Definition
Doing activities in parallel that would normally be done in sequence - often results in rework, and increases risk |
|
|
Term
|
Definition
Involves calculating multiple project durations with different set of activity assumptions. (usually done using a computer program) |
|
|
Term
Resource Leveling heuristics |
|
Definition
Mathematical Analysis often results in preliminary early-start schedule that requires more resources during certain time periods than are available. Heuristics (or Rule of Thumb) used to do Resource Leveling |
|
|
Term
|
Definition
Activities should have a coding structure to allow sorting and/or extractions based on different attributes assigned to the activities. |
|
|
Term
|
Definition
Includes planned start and expected finish dates for each activity |
|
|
Term
Project Schedule / Schedule Baseline |
|
Definition
Component of the project plan - provides basis for measuring and reporting schedule performance |
|
|
Term
|
Definition
Modification to the schedule information that is used to manage the project. |
|
|
Term
|
Definition
Special Category of schedule updates. They are changes to the schedule start and finish dates generally incorporated in response to scope changes or changes to estimates. |
|
|
Term
|
Definition
Done when schedule delays are very severe, and the project schedule has to be completely changed. |
|
|
Term
|
Definition
Done as part of corrective action - Helps identify the cause of variation, so that schedule recovery can be planned and executed for the activities delienated later in the schedule |
|
|
Term
Estimate Activity Durations : what are the inputs ? |
|
Definition
Activity List
Attributes
Project Schedule Network diagrams
Activity Resource Requiements
Resource Calandars
Acivity Duration estimates
Project Scope Statement
EEF
OPA |
|
|