Term
Define Activities (Time Management/Planning) Inputs
Definition

Scope baseline

Enterprise environmental factors

Organizational process assets

Term
Define Activities (Time Management/Planning) Tools & Techniques
Definition

Decomposition

Rolling wave planning

Templates Expert judgment

Term
Define Activities (Time Management/Planning) Outputs
Definition

Activity list

Activity attributes

Milestone list

Term
Sequence Activities (Time Management/Planning) Inputs
Definition

Activity List

Activity attributes

Milestone list

Project scope statement

Organizational process assets

Term
Sequence Activities (Time Management/Planning) Tools & Techniques
Definition

Precedence diagram method (PDM)

Dependency determination

Applying leads and lags

Schedule Network Templates

Term
Sequence Activities (Time Management/Planning) Outputs
Definition

Project schedule

network diagrams

Project document updates

Term
Estimate Activity Resources (Time Management/Planning) Inputs
Definition

Activity List

Activity attributes

Resource calendars

Enterprise environmental factors

Organizational process assets

Term
Estimate Activity Resources (Time Management/Planning) Tools & Techniques
Definition

Expert judgment

Alternative analysis

Published estimating data

Bottom-up estimating

Project Management software

Term
Estimate Activity Resources (Time Management/Planning) Outputs
Definition

Activity resource requirements

Resource breakdown structure

Project document updates

Term
Estimate Activity Durations (Time Management/Planning) Inputs
Definition

Activity list

Activity attributes

Activity resource requirements

Resource calendars

Project scope statement

Enterprise environmental factors

Organizational process assets

Term
Estimate Activity Durations (Time Management/Planning) Tools & Techniques
Definition

Expert judgment

Analogous estimating

Parametric estimating

Three-point estimates

Reserve analysis

Term
Estimate Activity Durations (Time Management/Planning) Outputs
Definition

Activity duration estimates

Project document updates

Term
Develop Schedule (Time Management/Planning) Inputs
Definition

Activity List

Activity attributes

Project Schedule

Network diagram

Activity Resource requirements

Resource Calendars

Activity duration estimates

Project scope statement

Enterprise Environmental Factors

Organizational process assets

Term
Develop Schedule (Time Management/Planning) Tools & Techniques
Definition

Schedule network analysis

Critical path method

Critical chain method

Resource leveling

What-if scenario analysis

Applying leads and lags

Schedule Compression

Scheduling tools

Term
Develop Schedule (Time Management/Planning) Outputs
Definition

Project Schedule

Schedule baseline

Schedule data

Project document updates

Term
Control Schedule (Time Management/Monitoring & Controlling) Inputs
Definition

Project management plan

Project schedule

Work performance information

Organizational process assets

Term
Control Schedule (Time Management/Monitoring & Controlling) Tools & Techniques
Definition

Performance reviews

Variance analysis

Project management software

Resource leveling

What-if scenario analysis

Adjusting leads and lags

Schedule compression

Scheduling tool

Term
Control Schedule (Time Management/Monitoring & Controlling) Outputs
Definition

Work performance measurements

Organizational proc. assets updates

Change requests

Project management plan updates

Project document updates