Term
What process are done during the initiating group process ? (9 by Rrita Mulcahl, 2 by PMBOK 5th edtion) |
|
Definition
1. Select project manager 2. Determine company culture and existing systems 3. Collect processes, procedures, and historical information 4. Divide large projects into phases 5. Uncover initial requirements, assumptions, risk, constraints, and existing agreements 6. Assess project and product feasibility within the given constraints 7. Create measurable objective 8. 4.1 Develop project charter 9. 13.1 Identify stakeholders and determine their expectations, influence, and impact
(Red represents information straight from the PMBOK 5th edition, The rest is from Rita Mulcahy’s PMP exam prep book) |
|
|
Term
What process are done during the planning group process (in order)? (24) |
|
Definition
1. Determine how you will plan for each knowledge area 2. determine detailed requirements 3. Create project scope statement 4. Assess what to purchase an create procurement documents 5. Determine planning team 6. 5.4 Create WBS and WBS dictionary 7. Create activity list 8. Create network diagram 9. 7.2 Estimate rescource requirements 10. Determine critical path 11. 6.1 Plan schedule management 12. 7.3 Develop budget 13. Determine quality standards, process and metrics 14. Create process improvement plan 15. Determine all roles and responsibilities 16. 10.1 Plan communication and stake holder engagement 17. 11.2 Perform risk identification,11.3 qualitative and 11.4 quantitative risk analysis and 11.5 risk response planning 18. Go back- iterations 19. 12.1 Finalize procurement document 20. Create change management 21. Finalize the “how to execute and control” parts of all management plans 22. Develop realistic and final PM plan and performance measurement baseline 23. Gain formal approval of plan 24. Hold kickoff meeting
(Red represents information straight from the PMBOK 5th edition, The rest is from Rita Mulcahy’s PMP exam prep book) |
|
|
Term
What process are done during the Executing group process ? (20) |
|
Definition
1. Execute the work according to the PM plan 2. 4.3 Producing product deliverables (product scope) 3. Gather work performance data 4. Request changes 5. Implement only approved change 6. Continuously improve 7. Follow process 8. Determine whether process are correct and effective (quality assurance) 9. 8.2 Perform quality audits 10. 9.2 Acquire final team 11. 9.4 Manage people 12. Evaluate team and individual performance 13. Hold team building activities 14. Give recognition and rewards 15. Use issue logs 16. Facilitate conflict resolution release resources as work is completed 17. Send and receive information, and solicit feedback 18. 13.3 Report on project performance manage stakeholder engagement and expectations 19. Hold meetings 20. Select sellers
(Red represents information straight from the PMBOK 5th edition, The rest is from Rita Mulcahy’s PMP exam prep book) |
|
|
Term
What process are done during the Monitoring and Controlling group process ? (19) |
|
Definition
1. Take action to control the project 2. Measure performance against the performance measurements baseline 3. Measure performance against other metrics in the PM plan 4. Analysis and evaluate performance 5. Determine if variances warrant a corrective action or other change request 6. Influence the factor that cause changes 7. Request changes 8. 4.5 Perform integrated change control 9. Approve or reject changes 10. Update the PM plan and project documents 11. Inform stakeholders of result change request 12. 13.4 Monitor stakeholder engagement 13. Manage configuration 14. Create forecasts 15. Gain acceptance of interim deliverables from the customer 16. Perform quality control 17. Perform risk reassessments and audits 18. Manage reserves 19. 12.3 Control procurements (Red represents information straight from the PMBOK 5th edition, The rest is from Rita Mulcahy’s PMP exam prep book) |
|
|
Term
What process are done during the closing group process ? (9) |
|
Definition
1. 4.6 Confirm work is done to requirements 2. 12.4 Complete procurement closure 3. Gain final acceptance of product 4. Complete financials closure 5. Hand off completed product 6. Solicit feedback from the customer about the project 7. Complete final performance reporting 8. Index and archive records 9. Gather final lessons learned and update knowledge base
(Red represents information straight from the PMBOK 5th edition, The rest is from Rita Mulcahy’s PMP exam prep book) |
|
|