Term
EV
Definition
Earned Value
Term
CV
Definition
Cost Variance
Term
ETC
Definition
Estimate To Complete
Term
SV
Definition
Schedule Variance
Term
AC
Definition
Actual Cost
Term
PV
Definition
Planned Value
Term
SPI
Definition
Schedule Performance Index
Term
EAC
Definition
Estimate At Completion
Term
CPI
Definition
Cost Performance Index
Term
ETC
Definition
Estimate to Complete