Term
What is the process of cost management? |
|
Definition
Plan Cost Management/ Estimate Costs /Determine Budget/ Control Costs |
|
|
Term
What is the key output of the plan cost management process? |
|
Definition
|
|
Term
What are the key inputs to the estimate Costs process? |
|
Definition
Cost management plan/ Scope baseline/ Project schedule/ Human resources management plan/ Risk register/ Enterprise environmental factors/ Organizational process assets |
|
|
Term
What are the key outputs of the Estimate costs process? |
|
Definition
Activity cost estimates/ Basis of estimates/ Updates to project documents |
|
|
Term
What are the key outputs of the Determine Budget process? |
|
Definition
Cost baseline/ Project funding requirements/ Updates to project documents |
|
|
Term
What are the key outputs of the control Costs process? |
|
Definition
Work performance information/ Cost forecasts/ Change request/ Updates to project management plan and project documents |
|
|
Term
What are the main approaches to cost or schedule estimating? |
|
Definition
One point estimating/ Analogous estimating/ Bottom up estimating/ Parametric estimating/ Three point estimating |
|
|
Term
What is analogous estimating? |
|
Definition
Top down estimating that uses expert judgment and historical information to predict the future) for example, ”The last here projects cost $25,000, or took six months and so should this one”) |
|
|
Term
What is bottom up estimating? |
|
Definition
Creating estimates based on the details of the project (e.g., from the bottom of the work breakdown structure), which are then rolled up into project estimates |
|
|
Term
What is parametric estimating? |
|
Definition
Calculating estimates by looking at the relationship between variables on an activity (e.g., cost per line of code, hours per installation, industry requirements, standard metrics, or other sources |
|
|
Term
What is earned value measurement, and how it is used? |
|
Definition
A method of measuring project performance that looks at the value earned for work accomplished, by reviewing project performance against the scope, schedule, and cost baseline. It can be used to predict future cost performance and project completion dates |
|
|
Term
What is the typical range for a rough order of magnitude (ROM) estimate? |
|
Definition
-25% to + 75% from actual |
|
|
Term
What is the typical range for budget estimate? |
|
Definition
|
|
Term
What is the typical range for a definitive estimate? |
|
Definition
|
|
Term
What is the difference between a cost budget and a cost baseline? |
|
Definition
The cost budget adds management reserves to the cost baseline |
|
|
Term
What is the formula for cost variance? |
|
Definition
|
|
Term
What is the formula for schedule variance? |
|
Definition
|
|
Term
What is the formula for cost performance index? |
|
Definition
|
|
Term
What is the formula for schedule performance index? |
|
Definition
|
|
Term
What are the formulas for estimate at completion? |
|
Definition
AC + Bottom-up ETC= EAC BAC/CPI© = EAC AC + (BAC-EV)=EAC AC + [(BAC-EV)/(CPI© X SPI©)]=EAC |
|
|
Term
What is the formula for estimate to complete? |
|
Definition
|
|
Term
What is the formula for variance at completion? |
|
Definition
|
|
Term
What is the formula for to complete performance index? |
|
Definition
[(BAC – EV)/(BAC – AC)]=TCPI |
|
|
Term
How doe variable cost differ from fixed costs? |
|
Definition
Variable cost vary with amount of production or work done on the project Fixed cost do not vary with the amount of production or work done on the project |
|
|
Term
What is a direct cost? What is an indirect cost? |
|
Definition
Direct cost: A cost that is directly attributable to the project Indirect cost: Overhead cost or cost incurred for more than one project |
|
|
Term
What does life cycle cost mean? |
|
Definition
Considering cost over the entire life of the product, not just the cost of the project to create the product |
|
|
Term
|
Definition
Finding a less costly way of doing essentially the same work (also known a value engineering) |
|
|