Term
What is the process of time management? |
|
Definition
Plan Schedule Management/ Define Activities/ Sequence Activities/ Estimate Activity/ Resources Estimate /activity Durations/ Develop Schedule/ Control Schedule |
|
|
Term
What is the key output of the Plan Schedule Management process? |
|
Definition
|
|
Term
What are the key outputs of the Define Activities process? |
|
Definition
Activity list/ Activity attributes/ Milestone List |
|
|
Term
What are the key outputs of the Sequence Activities process? |
|
Definition
Network diagrams Updates to project documents |
|
|
Term
What are some of the key outputs of the Estimate Activates Resources process? |
|
Definition
Activity resources requirements Resource breakdown structure |
|
|
Term
What are the key outputs of estimate Activity Durations process? |
|
Definition
Activity duration estimates Updates to project documents |
|
|
Term
What does the develop Schedule process involve? What are some of its key outputs? |
|
Definition
Creating a project schedule that is bought into, approved, realistic, and formal Project schedule Schedule baseline Updates to the project management plan and project documents |
|
|
Term
What are the key outputs of the control Schedule process? |
|
Definition
Work performance information Schedule forecast Change requests |
|
|
Term
What are the four type of logical relationships between activities in the precedence diagraming method? |
|
Definition
Finish to start(FS): An activity must finish before the successor can start Start to start (SS): An activity must start before the successor can start Finish to finish (FF): An activity must finish before the successor can finish Start to finish (SF): An activity must start before the successor can finish |
|
|
Term
What are mandatory dependencies? What are discretionary dependencies? |
|
Definition
Mandatory: the order in which activities MUST be done, due to the inherent nature of the work: also called “hard logic” Discretionary: The order in which the organization has chosen that activities be performed; also called preferred, preferential or soft logic |
|
|
Term
What are external dependencies? What are internal dependencies? |
|
Definition
External: Dependencies based on the needs of a party OUTSIDE the project Internal: Dependencies based on the project needs of the project; may be under the control of the project team |
|
|
Term
What is a lag? What is a lead? |
|
Definition
Lag: Waiting time inserted between activities Lead: How soon an activity can start before its procure activity can start before its predecessor activity is complemented |
|
|
Term
What is a resource breakdown structure? |
|
Definition
An organizational chart or table showing identified resources, organized by category and type |
|
|
Term
How does a schedule model differ from a schedule? |
|
Definition
The schedule model consists of all the project data that will used to calculate the schedule, such as the activities, dependencies leads and lags, etc. The project schedule is the output of the schedule model- this refers to the final, printed dates that make up the schedule that becomes the baseline and part of the project management plan |
|
|
Term
What is the critical path? What is the near critical path? |
|
Definition
Critical: The longest path through the network diagram Near-critical: The path closet in length to the critical path |
|
|
Term
How does the critical path help us manage the project? |
|
Definition
It shows the project manager the shortest time in which the project can be completed It shows the project manager where to focus his or her time It is used in compressing or adjusting the schedule. |
|
|
Term
Define total float, free float, and project float |
|
Definition
Total float: The amount of time an activity can be delayed without delaying the project and date or an intermediary milestone Free float: The amount of time an activity can be delayed without delaying the early start of its successors Project float: The amount of time the project can be delayed without affecting the projects required end date |
|
|
Term
What are the two formulas for calculating float? |
|
Definition
Late start- Early Start Or Late finish- Early finish |
|
|
Term
What are the methods that can be used to compress a schedule? |
|
Definition
|
|
Term
|
Definition
Adding or adjusting resource in order to compress the schedule while maintaining the original project scope |
|
|
Term
|
Definition
Compressing the schedule by doing more critical path activities in parallel |
|
|
Term
What is the critical chain method? |
|
Definition
A schedule network analysis tool that builds in buffers at critical milestones |
|
|
Term
|
Definition
Estimating the project again after planning to make sure you can still meet the end date, budget, or other objectives, and adjusting the project if you cannot |
|
|
Term
What is resources optimization? |
|
Definition
Finding ways to adjust the use of resources |
|
|
Term
What is a resource leveling? |
|
Definition
A resources optimization technique that keeps the amount of resources used for each time period constant, resulting in a more stable level of resources and a longer project duration |
|
|
Term
What is resource smoothing? |
|
Definition
A modified form of resource leveling, where resources are leveled only within the limits of the float of their activities, so the completion dates of activities are not delayed |
|
|
Term
What is the schedule baseline? |
|
Definition
The approved version of the schedule model, along with any approved changes, used to measure project schedule performance |
|
|
Term
What are the main presentation formats for a schedule? |
|
Definition
Network diagrams/ Bar Charts/ Milestone charts |
|
|
Term
What do network diagrams show? |
|
Definition
Dependencies (Logical relationships) between activities/ how project activities will flow from beginning to end/ network diagrams may also be used to determine the critical path |
|
|
Term
What do simple bar charts show? |
|
Definition
Project schedule or project status |
|
|
Term
What do milestone charts show? |
|
Definition
High level project status |
|
|
Term
What is Monte Carlo analysis? |
|
Definition
A schedule network analysis technique used to simulate the project to determine the likelihood that the project will be completed by a specific date or for a specific cost. Also used in Perform Quantitative Risk Analysis to determine the overall level of risk on the project |
|
|