Shared Flashcard Set

Details

PMP Acronyms
PMP Exam Certification 4th Edition
53
Business
Professional
11/19/2010

Additional Business Flashcards

 


 

Cards

Term
AC
Definition
Actual Cost
Term
ACWP
Definition
Actual cost of work performed
Term
BAC
Definition
Budget at Completion
Term
BCWP
Definition
Budgeted cost of work performed
Term
BCWS
Definition
Budgeted cost of work scheduled
Term
COQ
Definition
Cost of quality
Term
CPAF
Definition
Cost plus award fee
Term
CPF
Definition
Cost Plus fee
Term
CPFF
Definition
Cost plus fixed fee
Term
CPI
Definition
Cost performance index
Term
CPIF
Definition
cost plus incentive fee
Term
CPM
Definition
critical path methodology
Term
CV
Definition
Cost variance
Term
EAC
Definition
estimate at completion
Term
EF
Definition
Early finish date
Term
EMV
Definition
expected monetary value
Term
ES
Definition
early start date
Term
ETC
Definition
estimate to complete
Term
EV
Definition
earned value
Term
EVM
Definition
earned value management
Term
FF
Definition
finish to finish
Term
FFP
Definition
firm fixed price
Term
FMEA
Definition
failure mode and effect analysis
Term
FP-EPA
Definition
fixed price with economic price adjustment
Term
FPIF
Definition
fixed price incentive fee
Term
FS
Definition
finish to start
Term
IFB
Definition
invitation for bid
Term
LF
Definition
late finish date
Term
LOE
Definition
level of effort
Term
LS
Definition
late start date
Term
OBS
Definition
organizational breakdown structure
Term
PDM
Definition
precedence diagramming method
Term
PMBOK
Definition
Project Management Body of Knowledge
Term
PMIS
Definition
Project management information system
Term
PMP
Definition
project management professional
Term
PV
Definition
planned value
Term
QA
Definition
quality assurance
Term
QC
Definition
Quality Control
Term
RACI
Definition
responsible, accountable, consult, and inform
Term
RAM
Definition
responsibility assignment matrix
Term
RBS
Definition
risk breakdown structure
Term
RFI
Definition
request for information
Term
RFP
Definition
request for proposal
Term
RFQ
Definition
request for quotation
Term
SF
Definition
start to finish
Term
SOW
Definition
statement of work
Term
SPI
Definition
schedule performance index
Term
SS
Definition
start to start
Term
SV
Definition
schedule variance
Term
SWOT
Definition
strengths, weaknesses, opportunities, and threats
Term
TQM
Definition
total quality management
Term
WBS
Definition
work breakdown structure
Term
CCB
Definition
Change Control board
Supporting users have an ad free experience!