Shared Flashcard Set

Details

PMI Lexicon
PMI Vocab
190
Other
Graduate
01/24/2016

Additional Other Flashcards

 


 

Cards

Term
Acceptance Criteria
Definition
A set of conditions that are met before deliverables are accepted
Term
Activity
Definition
A distinct, scheduled portion of work performed during the course of a project.
Term
Activity Code
Definition
An alphanumeric value assigned to each activity that enables classifying, sorting, and filtering.
Term
Activity Identifier
Definition
A unique alphanumeric value assigned to an activity and used to differentiate that activity from other activities
Term
Activity Label
Definition
A phrase that names and describes an activity
Term
Actual Cost (AC).
Definition
The realized cost incurred for the work performed on an activity during a specific time period
Term
Analogous Estimating
Definition
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project
Term
Apportioned Effort
Definition
An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts.
Term
Assumption.
Definition
A factor in the planning process considered to be true, real, or certain, without proof or demonstration
Term
Backward Pass
Definition
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date
Term
Baseline.
Definition
The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results
Term
Bottom-Up Estimating
Definition
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Term
Budget at Completion (BAC).
Definition
The sum of all budgets established for the work to be performed
Term
Change Control
Definition
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected
Term
Change Control Board
Definition
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions
Term
Change Control System
Definition
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled.
Term
Change Request
Definition
A formal proposal to modify any document, deliverable, or baseline
Term
Code of Accounts
Definition
A numbering system used to uniquely identify each component of the work breakdown structure
Term
Communications Management Plan
Definition
A component of the project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated
Term
Configuration Management System
Definition
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts.
Term
Constraint
Definition
A limiting factor that affects the execution of a project, program, portfolio, or process
Term
Contingency Plan
Definition
A document describing actions that the project team can take if predetermined trigger conditions occur.
Term
Contingency Reserve
Definition
Time or money allocated in the schedule or cost baseline for known risks with active response strategies
Term
Control Account
Definition
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement
Term
Corrective Action
Definition
An intentional activity that realigns the performance of the project work with the project management plan.
Term
Cost Baseline
Definition
The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures and is used as the basis for comparison to actual results
Term
Cost Management Plan
Definition
A component of a project or program management plan that describes how costs will be planned, structured, and controlled
Term
Cost Performance Index (CPI).
Definition
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
Term
Cost Variance (CV).
Definition
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost
Term
Crashing
Definition
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.
Term
Critical Chain Method
Definition
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.
Term
Critical Path
Definition
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration
Term
Critical Path Activity
Definition
Any activity on the critical path in a project schedule. See also critical path and critical path method.
Term
Critical Path Method
Definition
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model
Term
Data Date
Definition
A point in time when the status of the project is recorded.
Term
Decision Tree Analysis
Definition
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.
Term
Decomposition
Definition
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
Term
Defect Repair
Definition
An intentional activity to modify a nonconforming product or product component
Term
Deliverable.
Definition
Any unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project.
Term
Discrete Effort
Definition
An activity that can be planned and measured and that yields a specific output
Term
Duration
Definition
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks
Term
Early Finish Date
Definition
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints
Term
Early Start Date
Definition
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints
Term
Earned Value (EV)
Definition
The measure of work performed expressed in terms of the budget authorized for that work
Term
Earned Value Management
Definition
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
Term
Effort
Definition
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks
Term
Enterprise Environmental Factors
Definition
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio.
Term
Estimate at Completion (EAC)
Definition
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete
Term
Estimate to Complete (ETC)
Definition
The expected cost to finish all the remaining project work
Term
Fast Tracking
Definition
A schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration
Term
Finish-to-Finish
Definition
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished
Term
Finish-to-Start
Definition
A logical relationship in which a successor activity cannot start until a predecessor activity has finished
Term
Fixed Formula Method
Definition
A method of estimating earned value in which a specified percentage of the budget value of a work package is assigned to the start milestone and the remaining percentage is assigned when the work package is complete.
Term
Forward Pass
Definition
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time
Term
Free Float
Definition
The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint
Term
Functional Organization.
Definition
An organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resource
Term
Gantt Chart
Definition
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates.
Term
Human Resource Management Plan.
Definition
A component of the project or program management plan that describes the roles and responsibilities, reporting relationships, and staff management
Term
Issue.
Definition
A threat that has occurred
Term
Lag.
Definition
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity
Term
Late Finish Date.
Definition
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the project completion date, and any schedule constraints
Term
Late Start Date.
Definition
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints
Term
Lead.
Definition
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity
Term
Lessons Learned.
Definition
The knowledge gained during a project which shows how project events were addressed or should be addressed in the future for the purpose of improving future performance.
Term
Level of Effort.
Definition
An activity that does not produce definitive end products and is measured by the passage of time.
Term
Logical Relationship.
Definition
A dependency between two activities or between an activity and a milestone
Term
Management Reserve.
Definition
Time or money that management sets aside in addition to the schedule or cost baseline and releases for unforeseen work that is within the scope of the project.
Term
Matrix Organization.
Definition
An organizational structure in which the project manager shares authority with the functional manager temporarily to assign work and apply resources
Term
Milestone.
Definition
A significant point or event in a project, program, or portfolio
Term
Milestone Schedule.
Definition
A type of schedule that presents milestones with planned dates
Term
Most Likely Duration.
Definition
An estimate of the most probable activity duration that takes into account all of the known variables that could affect performance
Term
Near-Critical Activity.
Definition
An activity with a total float that is deemed to be low based on expert judgment
Term
Near-Critical Path.
Definition
A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project
Term
Network Logic.
Definition
All activity dependencies in a project schedule network diagram
Term
Network Path.
Definition
A sequence of activities connected by logical relationships in a project schedule network diagram
Term
Node.
Definition
A point at which dependency lines connect on a schedule network diagram
Term
Opportunity.
Definition
A risk that would have a positive effect on one or more project objectives
Term
Optimistic Duration.
Definition
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance
Term
Organizational Breakdown Structure.
Definition
A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities
Term
Organizational Enabler.
Definition
Organizational Enabler. A structural, cultural, technological, or human-resource practice that the performing organization can use to achieve strategic objectives
Term
Organizational Process Assets.
Definition
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization.
Term
Organizational Project Management.
Definition
A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives
Term
Organizational Project Management Maturity.
Definition
The level of an organization’s ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner.
Term
Parametric Estimating.
Definition
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters
Term
Path Convergence.
Definition
A relationship in which a schedule activity has more than one predecessor
Term
Path Divergence.
Definition
A relationship in which a schedule activity has more than one successor
Term
Percent Complete.
Definition
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component
Term
Performance Measurement Baseline.
Definition
Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution
Term
Performing Organization.
Definition
An enterprise whose personnel are the most directly involved in doing the work of the project or program
Term
Pessimistic Duration.
Definition
An estimate of the longest activity duration that takes into account all of the known variables that could affect performance
Term
Phase Gate.
Definition
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program
Term
Planned Value (PV).
Definition
The authorized budget assigned to scheduled work
Term
Portfolio.
Definition
Projects, programs, subportfolios, and operations managed as a group to achieve strategic objectives
Term
Portfolio Balancing.
Definition
The process of optimizing the mix of portfolio components to further the strategic objectives of the organization
Term
Portfolio Charter.
Definition
A document issued by a sponsor that authorizes and specifies the portfolio structure and links the portfolio to the organization’s strategic objectives
Term
Portfolio Management.
Definition
The centralized management of one or more portfolios to achieve strategic objectives
Term
Portfolio Management Plan.
Definition
A document that specifies how a portfolio will be organized, monitored, and controlled
Term
Portfolio Manager.
Definition
The person or group assigned by the performing organization to establish, balance, monitor, and control portfolio components in order to achieve strategic business objectives
Term
Precedence Diagramming Method.
Definition
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed
Term
Predecessor Activity.
Definition
An activity that logically comes before a dependent activity in a schedule
Term
Preventive Action.
Definition
An intentional activity that ensures the future performance of the project work is aligned with the project management plan
Term
Probability and Impact Matrix.
Definition
A grid for mapping the probability of occurrence of each risk and its impact on project objectives if that risk occurs
Term
Procurement Management Plan.
Definition
A component of the project or program management plan that describes how a team will acquire goods and services from outside of the performing organization
Term
Product Life Cycle.
Definition
The series of phases that represent the evolution of a product, from concept through delivery, growth, maturity, and to retirement
Term
Program.
Definition
A group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits not available from managing them individually
Term
Program Charter.
Definition
A document issued by a sponsor that authorizes the program management team to use organizational resources to execute the program and links the program to the organization’s strategic objectives
Term
Program Evaluation and Review Technique (PERT).
Definition
A technique used to estimate project duration through a weighted average of optimistic, pessimistic, and most likely activity durations when there is uncertainty with the individual activity estimates
Term
Program Management.
Definition
The application of knowledge, skills, tools, and techniques to a program to meet the program requirements and to obtain benefits and control not available by managing projects individually
Term
Program Management Office.
Definition
A management structure that standardizes the program-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
Term
Program Management Plan.
Definition
A document that integrates the program’s subsidiary plans and establishes the management controls and overall plan for integrating and managing the program’s individual components
Term
Program Manager.
Definition
The person authorized by the performing organization to lead the team or teams responsible for achieving program objectives
Term
Progressive Elaboration.
Definition
The iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available
Term
Project.
Definition
A temporary endeavor undertaken to create a unique product, service, or result
Term
Project Budget.
Definition
The sum of work package cost estimates, contingency reserve, and management reserve
Term
Project Calendar
Definition
A calendar that identifies working days and shifts that are available for scheduled activities
Term
Project Charter.
Definition
A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities
Term
Projectized Organization.
Definition
An organizational structure in which the project manager has full authority to assign work and apply resources
Term
Project Life Cycle.
Definition
The series of phases that a project passes through from its initiation to its closure
Term
Project Management.
Definition
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements
Term
Project Management Office.
Definition
A management structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques
Term
Project Management Plan.
Definition
The document that describes how the project will be executed, monitored and controlled, and closed
Term
Project Manager.
Definition
The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives
Term
Project Phase.
Definition
A collection of logically related project activities that culminates in the completion of one or more deliverables
Term
Project Schedule.
Definition
An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
Term
Project Schedule Network Diagram.
Definition
A graphical representation of the logical relationships among the project schedule activities
Term
Project Scope.
Definition
The work performed to deliver a product, service, or result with the specified features and functions.
Term
Project Scope Statement.
Definition
The description of the project scope, major deliverables, assumptions, and constraints.
Term
Quality Management Plan.
Definition
A component of the project or program management plan that describes how an organization’s quality policies will be implemented
Term
Residual Risk.
Definition
The risk that remains after risk responses have been implemented
Term
Resource Breakdown Structure.
Definition
A hierarchical representation of resources by category and type
Term
Resource Calendar.
Definition
A calendar that identifies the working days and shifts upon which each specific resource is available
Term
Resource Leveling.
Definition
A resource optimization technique in which adjustments are made to the project schedule to optimize the allocation of resources and which may affect critical path
Term
Resource Optimization Technique.
Definition
A technique in which activity start and finish dates are adjusted to balance demand for resources with the available supply
Term
Resource Smoothing.
Definition
A resource optimization technique in which free and total float are used without affecting the critical path
Term
Responsibility Assignment Matrix.
Definition
A grid that shows the project resources assigned to each work package
Term
Requirement.
Definition
A condition or capability that is required to be present in a product, service, or result to satisfy a contract or other formally imposed specification
Term
Requirements Management Plan.
Definition
A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed
Term
Requirements Traceability Matrix.
Definition
A grid that links product requirements from their origin to the deliverables that satisfy them.
Term
Risk.
Definition
An uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives
Term
Risk Acceptance.
Definition
A risk response strategy whereby the project team decides to acknowledge the risk and not take any action unless the risk occurs
Term
Risk Appetite.
Definition
The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward
Term
Risk Avoidance.
Definition
A risk response strategy whereby the project team acts to eliminate the threat or protect the project from its impact
Term
Risk Breakdown Structure.
Definition
A hierarchical representation of risks that is organized according to risk categories
Term
Risk Category.
Definition
A group of potential causes of risk
Term
Risk Enhancement.
Definition
A risk response strategy whereby the project team acts to increase the probability of occurrence or impact of an opportunity
Term
Risk Exploiting.
Definition
A risk response strategy whereby the project team acts to ensure that an opportunity occurs
Term
Risk Exposure.
Definition
An aggregate measure of the potential impact of all risks at any given point in time in a project, program, or portfolio.
Term
Risk Management Plan.
Definition
A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed
Term
Risk Mitigation.
Definition
A risk response strategy whereby the project team acts to decrease the probability of occurrence or impact of a threat
Term
Risk Owner.
Definition
The person responsible for monitoring the risk and for selecting and implementing an appropriate risk response strategy
Term
Risk Register.
Definition
A repository in which outputs of risk management processes are recorded
Term
Risk Sharing.
Definition
A risk response strategy whereby the project team allocates ownership of an opportunity to a third party who is best able to capture the benefit for the project
Term
Risk Threshold.
Definition
The level of risk exposure above which risks are addressed and below which risks may be accepted
Term
Risk Tolerance.
Definition
The degree of uncertainty that an organization or individual is willing to withstand
Term
Risk Transference.
Definition
A risk response strategy whereby the project team shifts the impact of a threat to a third party, together with ownership of the response
Term
Rolling Wave Planning.
Definition
An iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level
Term
Schedule Baseline.
Definition
The approved version of a schedule model that can be changed using formal change control procedures and is used as the basis for comparison to actual results
Term
Schedule Compression.
Definition
A technique used to shorten the schedule duration without reducing the project scope
Term
Schedule Management Plan.
Definition
Schedule Management Plan. A component of the project or program management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule
Term
Schedule Model.
Definition
A representation of the plan for executing the project’s activities, including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts
Term
Schedule Model Analysis.
Definition
A process used to investigate or analyze the output of the schedule model in order to optimize the schedule
Term
Schedule Network Analysis.
Definition
A technique to identify early and late start dates, as well as early and late finish dates, for the uncompleted portions of project activities
Term
Schedule Performance Index (SPI).
Definition
A measure of schedule efficiency expressed as the ratio of earned value to planned value
Term
Schedule Variance (SV).
Definition
A measure of schedule performance expressed as the difference between the earned value and the planned value
Term
Scope Baseline.
Definition
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results
Term
Scope Creep.
Definition
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources
Term
Scope Management Plan.
Definition
A component of the project or program management plan that describes how the scope will be defined, developed, monitored, controlled, and validated
Term
S-Curve Analysis.
Definition
A technique used to indicate performance trends by using a graph that displays cumulative costs over a specific time period
Term
Secondary Risk.
Definition
A risk that arises as a direct result of implementing a risk response
Term
Sponsor.
Definition
An individual or a group that provides resources and support for the project, program, or portfolio, and is accountable for enabling success
Term
Staffing Management Plan.
Definition
A component of the human resource plan that describes when and how team members will be acquired and how long they will be needed
Term
Stakeholder.
Definition
An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project, program, or portfolio
Term
Stakeholder Management Plan.
Definition
A component of the project management plan that describes how stakeholders will be engaged in project decision making and execution
Term
Start-to-Finish.
Definition
A logical relationship in which a successor activity cannot finish until a predecessor activity has started
Term
Start-to-Start.
Definition
A logical relationship in which a successor activity cannot start until a predecessor activity has started
Term
Successor Activity.
Definition
A dependent activity that logically comes after another activity in a schedule
Term
Summary Activity.
Definition
A group of related schedule activities aggregated and displayed as a single activity
Term
Threat.
Definition
A risk that would have a negative effect on one or more project objectives
Term
Three-Point Estimating.
Definition
A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates
Term
To-Complete Performance Index (TCPI).
Definition
A measure of the cost performance that is achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget
Term
Total Float.
Definition
The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Term
Trigger Condition.
Definition
An event or situation that indicates that a risk is about to occur
Term
Variance Analysis.
Definition
A technique for determining the cause and degree of difference between the baseline and actual performance
Term
Variance at Completion (VAC).
Definition
A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion
Term
WBS Dictionary.
Definition
A document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure
Term
Weighted Milestone Method.
Definition
A method of estimating earned value in which the budget value of a work package is divided into measurable segments, each ending with a milestone that is assigned a weighted budget value
Term
What-If Scenario Analysis.
Definition
The process of evaluating scenarios in order to predict their effect on project objectives
Term
Workaround.
Definition
An immediate and temporary response to an issue, for which a prior response had not been planned or was not effective
Term
Work Breakdown Structure (WBS).
Definition
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables
Term
Work Package.
Definition
The work defined at the lowest level of the work breakdown structure for which cost and duration can be estimated and managed.
Supporting users have an ad free experience!