series of related jobs directed toward some major output and requiring time to perform |
|
|
Term
|
Definition
planning, directing, and controlling resources to meet the techonology, cost, and time considerations |
|
|
Term
|
Definition
a self-contained team works full time on project
1 boss quick decisions increased motivation
duplication of resources |
|
|
Term
|
Definition
housing project within functional division
several projects expertise
low motivation slow response |
|
|
Term
|
Definition
|
|
Term
|
Definition
written description of objectives to be achieved; brief statement of work to be done, proposed schedule, could include milestones |
|
|
Term
|
Definition
|
|
Term
|
Definition
groups of activities combined to be assigned to single organizational unit |
|
|
Term
|
Definition
specific events to be reached at a certain time |
|
|
Term
|
Definition
defines the heirarchy of tasks and work packages |
|
|
Term
|
Definition
pieces of work that take time |
|
|
Term
|
Definition
bar chart; shows time and sequence |
|
|
Term
Total Program Cost Breakdown |
|
Definition
labor, materials, and overhead |
|
|
Term
Divisional Breakdown of Cost and Labor |
|
Definition
% of labor hours from each division |
|
|
Term
Cost and Performance Tracking Schedule |
|
Definition
|
|
Term
|
Definition
technique for measuring project progress objectively; scope,schedule, cost
essential features: project plan ids activities; valuation of each activity (revenue and cost); predefined earning/costing rates |
|
|
Term
|
Definition
procedure for scheduling a project
id activities and estimate time determine sequence and network construction determine critical path determine ES/LS and EF/LF determine slack time |
|
|
Term
|
Definition
sequence of activities that form the longest chain |
|
|
Term
|
Definition
attempt to develop a minimum cost schedule to control expenditures |
|
|
Term
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
prepare CPM netowrk diagram; normal and crash cost/time
determine cost/day to expedite each activity
compute critical path
decrease CP at lowest cost
plot direct indirect and total cost curves and find minimum cost schedule |
|
|