WHEN TESTING RELIEF VALVES ON THE FIN STABILIZER, PUT GUAGES ON:
Definition
TS4 AND TS5 ON THE MAIN HYDRAULIC DISTRIBUTION MANIFOLD.
Term
WHEN REMOVING AIR IMPURITIES SUCH AS DUST, FUMES, SMOKE, AND VAPOR IS CALLED WHAT PROCESS?
Definition
PURIFICATION
Term
THE PROCESS OF MOVING STALE AIR AND PROVIDING FRESH AIR IS CALLED:
Definition
VENTILATION
Term
THE MOVEMENT OF AIR THROUGH A NATURAL MEANS IS:
Definition
AIR CIRCULATION
Term
IF THE DIFFERENCE BETWEEN Tw AND Ts IS OVER 4 DEGREES, THEN THE:
Definition
INTAKE AIR IS BEING HEATED IN THE SUPPLY DUCT
Term
IN DEMPS, WHAT SHALL BE PLOTTED ON GRAPH PAPER?
Definition
CRANKCASE VACUUM, INTAKE AIR PRESSURE, EXHAUST PRESSURE, AND LUBE OIL CONSUMPTION
Term
MAINTENANCE PERSONNEL SHALL KNOW THE NORMAL RUNNING TEMPS OF EACH BEARING UNDER ALL CONDITIONS OF:
Definition
LOAD, SPEED, AND INVESTIGATE ANY CHANGES IMMEDIATLY.
Term
SURFACE INSPECTIONS OF COMPRESSED AIR SYSTEMS ARE PERFORMED:
Definition
SEMI-ANNUALLY (EVERY 6 MONTHS)
Term
A PHYSICAL INVENTORY IS TAKEN TO VERIFY THE EXISTENCE OF A SPECIFIC STOCK ITEM IS CALLED A:
Definition
SPOT INVENTORY
Term
REVERSE OSMOSIS SYSTEMS SHOULD BE QUIET AND FREE FROM EXCESSIVE:
Definition
VIBRATIONS, CLICKING OR METALLIC NOISES
Term
FAILURE TO REMOVE CLEANING FLUIDS FROM SEALING SURFACES COULD CAUSE:
Definition
SOME "O"RINGS TO SWELL AND INTERFERE WITH PERFORMANCE OR CAUSE SEAL FAILURE.
Term
IF YOU LOSE SUCTION ON A P-250 PUMP DUE TO LEAKY HOSE:
Definition
REPAIR OR REPLACE SUCTION HOSE
Term
IF WATER PRIMING PUMP ON P-250 WON'T PRIME:
Definition
IT IS NOT A BAD FUEL LINE.
Term
THERE SHOULD BE NO MORE THAN ____ INCHES Hg OF VACUUM LOST IN 10 MINUTES ON A P-250 VACUUM TEST
Definition
10 INCHES OF Hg
Term
IF P-250 ENGINE MISFIRES IT COULD BE THE:
Definition
VRO PUMP (VARIO RATIO OILER)
Term
TO TEST RESISTANCE ON A CHARGE COIL, CALIBRATE OHMETER TO A MEDIUM:
Definition
(X 100 OHMS) SCALE
Term
TO CHECK IF CHARGE COIL IS SHORTED TO GROUND, CALIBRATE OHMMETER TO HIGH:
Definition
(X 10,000 OHMS) SCALE
Term
TO CHECK SENSOR COIL RESISTANCE, CALIBRATE OHMMETER TO A MEDIUM:
Definition
(X 10 OHMS) SCALE
Term
TO CHECK IF SENSOR COIL IS SHORTED TO GROUND, CALIBRATE OHMMETER TO A HIGH
Definition
(X 10,000 OHMS) SCALE
Term
CHARGER COIL RESISTANCE READINGS SHOULD BE:
Definition
575 +/- 75 OHMS
Term
IF SLUGGING OCCURS IN THE EVAP YOU:
Definition
REDUCE INJECTION RATE BY 40-50%
Term
IF SCALING OCCURES IN THE EVAP YOU:
Definition
INCREASE INJECTION RATE BY 40-50%
Term
IF WASHER DOES NOT DRAIN DUE TO MANIFOLD AIR LOCK:
Definition
ENSURE BLEED HOLE IS CLEAR.
Term
TEST THE BRAKES ON A DAVIT BY HOLDING THE LOAD STATIONARY FOR AT LEAST:
Definition
1 MINUTE
Term
FOR STATIC LOAD TEST OF A DAVIT SUSPENDED THE TEST WEIGHT FROM THE BOAT HOOK FOR A PERIOD OF:
Definition
10 MINUTES
Term
THE STATIC LOAD TEST IS PERFORMED AT ___ OF THE DAVIT'S RATED LOAD:
Definition
200%
Term
THE DYNAMIC LOAD TEST IS PERFORMED AT ___ OF THE DAVIT'S RATED LOAD:
Definition
150%
Term
THE RATED LOAD TEST IS PERFORMED AT ___ OF THE DAVIT'S RATED LOAD:
Definition
100%
Term
THIS CHEMICAL IS USED TO DISINFECT POTABLE WATER:
Definition
CALCIUM HYPOCHLORITE (HTH)
Term
THE WATER TESTS ARE IMPORTANT BECAUSE SAFETY OF THE WATER IS DEPENDANT ON:
Definition
RESIDUAL CONCENTRATIONS OF FREE AVAILABLE CHLORINE (FAC) OR BROMINE
Term
THESE ARE REQUIRED ONLY IN EXHAUST DUCTS FROM COMPARTMENTS THAT COULD PRODUCE EXPLOSIVE VAPORS:
Definition
FLAME ARRESTORS
Term
CAREFULLY REMOVE THE STEAM FEED HEATER TO PREVENT DAMAGE TO THE:
Definition
TUBES AND BAFFLES
Term
WHEN ON THE EXECUTIVE COMMAND BAR, TYPE ___ ___ AND PRESS RETURN.
Definition
FORMAT DISK
Term
THIS SYSTEM IS DESIGNED TO SUPPORT A CUTTER'S MISSION:
Definition
CM PLUS
Term
ON LEVEL II INSPECTION AND OVERHAUL TEST PADEYES TO:
Definition
200% OF THE DESIGNED WORKING LOAD
Term
RECIRC. SERVICE TANKS THROUGH HOSE AND FILTER/SEPERATOR FOR ___ AND THROUGH THE NOZZLE FOR ___ BEFORE TAKING "CLEAR AND BRIGHT" AND/OR WATER AND SEDIMENT TEST:
Definition
1 HOUR/ AT LEAST 5 MINUTES
Term
WHAT ARE THE TWO MOST WIDELY USED BEARING PULLERS IN THE CG?
Definition
TYPE I AND TYPE VII
Term
WHO SIGNS THE DD 1149 FOR ANYTHING OTHER THAN BULK FUEL:
Definition
SUPPLY OFFICER
Term
THE CSMP'S ARE USED FOR REQUESTING:
Definition
MAINTENANCE AND REPAIRS FOR AFLOAT UNITS
Term
QUALIFICATION LETTERS ARE FILED WHERE:
Definition
PERSONAL DATA RECORD (PDR)
Term
UNDER A LOAD THE P-5 WILL RUN FOR:
Definition
1.5-2.5 HOURS ON A GALLON OF GAS
Term
WHEN CHECKING IF IGNITION COIL IS SHORTED TO GROUND ON A P-250, RESISTANCE SHOULD READ
Definition
275 +/- 50 OHMS
Term
WHAT INSTRUCTION PROVIDES AUTHORITY TO DIVERT WASTES OVERBOARD WHILE WITHIN RESTRICTED WATERS WITHOUT VIOLATING FEDERAL, STATE, OR LOCAL LAWS?
Definition
OPNAVINST 5090.1
Term
HOW MUCH OIL OF AN OIL SAMPLE FOR AN OIL INSPECTION OF A WARPING CAPSTAN SHOULD YOU TAKE:
Definition
APPROX. 1 QUART
Term
FOR PUMP ALIGNMENT SHIMS SHALL BE MADE FROM:
Definition
304 STAINLESS STEEL
Term
ORDER OF PRECEDENCE WHEN OREDRING SUPPLIES:
Definition
1) AGENCY INVENTORY, 2) EXCESS PROPERTY, 3) FEDERAL PRISON INDUSTRIES
Term
A PHYSICAL INVENTORY IS TO:
Definition
ENSURE ACCURACY OF RECORDS
Term
WHEN STARTING A REEFER COMPRESSOR, JOG THE COMPRESSOR SEVERAL TIMES TO REMOVE:
Definition
REFRIGERENT FROM THE OIL
Term
WHAT TYPE OF OIL IS USED IN THE FIN STABILIZER?
Definition
MIL-L 17672 (2135)
Term
ON A STEERING RAM, HOW MUCH OIL LEAKAGE IS ALLOWED?
Definition
1/2 PINT DURING A 24 HOUR PERIOD
Term
IN THE AFT NFU MODE, SET THE MOTOR CONTROLLER TO THE:
Definition
AFT RUN POSITION
Term
AFTER REMOVING THE FIRING HEAD FROM THE BOILER, INSPECT THE:
Definition
ELECTRODES
Term
ACTIVITY, WEIGHT, AND DATE ARE REQUIRED ON THE LABEL PLATE, NOT THE:
Definition
PERSONS NAME
Term
CLEAN THE PHOTOCONDUCTIVE LENS ON A BOILER WITH A:
Definition
LINT-FREE RAG
Term
VISUAL INSPECTION, DETECTOR KIT, AND LABORATORY ANALYSIS ARE APPROVED TESTS FOR JP-5 NOT:
Definition
SULFUR CONTENT TEST
Term
THIS IS NOT A CAUSE OF NOISE OR VIBRATION OF A FIXED FIRE PUMP:
Definition
TOO BIG OF A SUCTION LIFT
Term
WHEN ADDING FLUID TO A HYDRAULIC SYSTEM, USE A FILTER WITH A NOMINAL RATING OF:
Definition
10 MICROMETERS
Term
ON THE OWS THE CYCLING EFFECT IS INDICATED BY RAPID CHANGES IN THE PRESSURE READINGS ON THE:
Definition
OUTLET PRESSURE OF THE PRE-FILTER STAGE AND THE OUTLET PRESSURE OF THE FIRST STAGE SEPERATOR
Term
THE AIR REGULATOR ON AN OWS IS SET AT:
Definition
30 PSI
Term
THE PRESSURE RELIEF VALVE ON AN OWS IS USED TO PREVENT THE OIL/WATER PUMP DISCHARGE PRESSURE FROM EXCEEDING:
Definition
50 PSI
Term
A MECHANICAL SEAL IS A SEAL DEVICE IN WHICH SEALING ACTION IS AIDED BY:
Definition
MECHANICAL FORCE
Term
WIPE "O"RINGS TO PREVENT:
Definition
SHRINKAGE AND SEAL FAILURE
Term
LAST THING TO BE SECURED WHEN RETURNING SYSTEM TO NORMAL AFTER HOT GAS DEFROSTING:
Definition
DE-ENERGIZE ELECRIC HEATING CABLES
Term
TO SECURE REFRIGERANT GOING TO THE EVAPORATOR COIL YOU CLOSE THE:
Definition
LIQUID CUT-OUT VALVE
Term
___ ARE PRIMARY IDEAS OR STEPS NECESSARY TO REACH THE OBJECTIVES SHOULD BE ARRANGED AND PRESENTED IN A LOGICAL ORDER.
Definition
MAIN TEACHING POINTS
Term
WHAT IS THE OBJECTIVE OF A LESSON PLAN?
Definition
IT IS A DOCUMENT DESCRIBING HOW A TRAINING LESSON WILL BE PRESENTED
Term
DO NOT MIX HYDRAULIC FLUID BECAUSE THEY MAY HAVE:
Definition
DIFFERENT ADDITIVES
Term
REPLACE THE CONDENSOR IF OVER ___ OF THE TOTAL TUBES OR ___ OF THE TUBES IN ANY ONE PASS NEED TO BE PLUGGED OR REPLACED DUE TO CORROSION.
Definition
10%
Term
WHAT IS LOCATED BETWEEN THE OUTLET PRESSURE GAUGE FOR THE PRE-FILTER STAGE AND THE OUTLET PRESSURE GAUGE FOR THE FIRST STAGE SEPERATOR?
Definition
AIR REGULATOR
Term
WHEN WORKING ON WATER COOLED CONDENSORS, BE CAREFUL NOT TO DAMAGE THE GASKETS BETWEEN THE:
Definition
TUBE SHEETS AND THE WATERSIDE OF THE WATER HEADS
Term
HYDROSTATIC PRESSURE TEST FOR AIR SYSTEMS ON SHIP'S BUILT BEFORE 1969 SHALL NOT EXCEED THE:
Definition
VALUE SPECIFIED ON ORIGINAL SYSTEM DRAWINGS OR 150% OF THE NORMAL OPERATING PRESSURE
Term
AIR SYSTEMS BUILT AFTER 1969, THE TEST PRESSURE IS:
Definition
135% OF DESIGN PRESSURE
Term
ON A REFRIGERATION SYSTEM, TURN THIS ON WHEN SECURED TO EVAPORATE REFRIGERANT TRAPPED INSIDE THE OIL:
Definition
COMPRESSOR CRANKCASE HEATER
Term
BRUSH THE TUBES ON THE FIRESIDE OF A BOILER WITH THE:
Definition
PROPER SIZE TUBE BRUSH
Term
TO REMOVE LOOSE SOOT FROM THE FIRESIDE OF A BOILER USE:
Definition
INDUSTRIAL TYPE VACUUM CLEANER
Term
TO CLEAN THE INSULATION OF THE FIRESIDE, USE A:
Definition
NATURAL FIBER BRUSH
Term
TO REMOVE SCALE FROM THE WATERSIDE OF A BOILER USE:
Definition
HIGH PRESSURE (50-60 PSI) WATER HOSE
Term
RIGGING GEAR MUST BE TESTED TO:
Definition
1 1/2 TIMES ITS SAFE WORKING LOAD EACH YEAR
Term
TOTAL HP OF ENGINE BEING INSTALLED SHOULD BE NO LESS THAN:
Definition
70% OF BOATS CERTIFICATION PLATE
Term
TILT CYLINDER MOVES ENGINE THROUGH THE FINAL:
Definition
50 DEGREES OF MOTION (TILT RANGE)
Term
THREE METHODS OF REPORTING PROJECTS FOR SSMP'S:
Definition
SHORE STATION MAINT. RECORD (SSMR), CASUALTY REPORT (CASREP), MESSAGE/LETTER.
Term
WHAT FORM IS USED EXTENSIVELY BY CG ORDANCE DEPARTMENTS:
Definition
OPNAV 4790-2K
Term
THE THREE BASIC TYPES OF REVISIONS ARE:
Definition
REISSUE, PAGE REPLACEMENT, PEN CHANGE
Term
ORDER OF PRIORTY WHEN SERVICES:
Definition
PURCHASE FROM BLIND, MANDATORY FEDERAL SUPPLY SCHEDULE, OPTIONAL USER FEDERAL SUPPLY SCHEDULE, FEDERAL PRISON INDUSTRIES,INC.
Term
THE REVERSE LOCK CHECK VALVE ALLOWS OIL TO FLOW FROM THE PUMP TO THE TOP SIDES OF THE TRIM/TILT CYLINDERS DURING:
Definition
TRIM-IN/TILT-DOWN
Term
REPLACE PACKING WHEN LEAKAGE CAN NO LONGER BE CONTROLLED BY ADJUSTING THE:
Definition
GLAND NUT
Term
ON FUEL OIL PURIFIERS OPEN REGULATING VALVE (SV10) FOR DISPLACEMENT WATER:
Definition
ALL THE WAY
Term
CLOSE PURIFIER SUCTION FOR HOW LONG PRIOR TO STOPPING UNIT:
Definition
2 MIN
Term
HOW MANY VOLTS IS APPLIED TO STARTED TO A STARTER UNIT FOR A HIGH VOLTAGE TEST:
Definition
APPROXIMATELY 500 VOLTS
Term
BOXES SHOULD BE DEFOSTED WHEN THE FROST BUILD-UP IS:
Definition
3/16" THICK
Term
BOXES MUST BE DEFOSTED WHEN THE FROST BUILD-UP IS:
Definition
1/4" THICK
Term
NEVER ALLOW FROST BUILD-UP TO EXCEED:
Definition
1/4" THICK
Term
IF PRESSURE DIFFERENTIALS OR THE CORRESPONDING DIFFERENCES INCREASE BY 30%
Definition
THEN EVAP SHOULD BE ACID CLEANED.
Term
WHEN HYDRO TESTING AN EVAP, TEST 10 PSIG AND HOLD FOR AT LEAST:
Definition
1 HOUR
Term
WHEN TRANSFERING HYDRAULIC FLUID, ENSURE THAT THE FILTER ELEMENT USED HAS AN ABSOLUTE RATING OF ___ MICROMETERS, OR A NOMINAL RATING OF ___ MICROMETERS
Definition
25/10
Term
TO REMOVE TRAPPED AIR FROM A HYD. PUMP YOU:
Definition
LOOSEN PUMP DISCHARGE FITTING AND JOG ON/OFF OR MANUALLY LIFT THE RELIEF VALVE AT THE DISCHARGE SIDE OF A PUMP.
Term
HYDRAULIC FLUID SAMPLING CONTAINERS SHOULD BE:
Definition
CLEAN AND REUSEABLE
Term
WHEN LAPPING A VALVE SEAT, USE THIS GRADE FOR VALVES THAT ARE NOT SEVERLY DAMAGED:
Definition
MEDIUM GRADE ABRASIVE
Term
WHILE CONDUCTING THE TEST ON MAGNA-MATIC EQUIPPED ENGINES SET THE TESTER GAP TO:
Definition
.060 INCHES
Term
ALL INFORMATION ON FIXED FIRE FIGHTING PUMPS CAN BE FOUND IN:
Definition
NSTM CHAPTER 503, PUMPS
Term
CALCIUM HYPOCHLORITE MUST BE HANDLED AND STOWED IAW WITH:
Definition
NSTM CHAPTER 670, STORAGE, HANDLING, AND DISPOSAL OF HAZARDOUS GENERAL USE CONSUMABLES
Term
CHLORINE AND BROMINE ARE:
Definition
HALOGENS FOR TREATING POTABLE WATER
Term
THE THREE TESTS FOR ANCHOR WINDLASSES ARE:
Definition
NO-LOAD, DROP, AND RECOVERY TEST
Term
YOU MAINTAIN HOW MANY DEAD WRAPS ON A DRUM AT ALL TIMES:
Definition
FIVE DEAD WRAPS
Term
ON A FIRST LEVEL INSPECTION IF OIL IN GEARBOX IS MORE THAN FIVE GALLONS:
Definition
SEND SAMPLE OUT FOR SPECTROANALYSIS INSPECTION
Term
AIR SYSTEMS WITH MOISTURE SEPERATORS ARE REQUIRED METAL BOWLS:
Definition
FOR SERVICE ABOVE 125 PSIG
Term
IF THE DIFFERENCE BETWEEN Ts AND Ta IS OVER 10 DEGREES THEN:
Definition
AIR QUANITY IS LOW OR THERE IS AN INFLUX OF HOT AIR FROM OTHER SPACES
Term
ON A REVERSE OSMOSIS SYSTEM, DO NOT ADJUST THE SYSTEM TO EXCEED THE:
Definition
RATED FLOW CAPACITY OR MAXIMUM OPERATING PRESSURE