Shared Flashcard Set

Details

Law Final
Construction Law and Contracts Final Exam
45
Civil Engineering
Graduate
04/30/2012

Additional Civil Engineering Flashcards

 


 

Cards

Term

Type of Contract where the contractor has the most risk?

 

 

Where owner has the most risk?

Definition

Fixed price contract

 

 

Cost-reibursable contracts (Cost plus, GMP)

 

 

Term
Formula for determining $ surety obligations- Penal Sum?
Definition

See pg 133 for example

 

unpaid balance = k amt  - amt paid to contractor

 

Surety's obligation = Cost to complete - unpaid bal + liquidated dmgs

 

-only pay up to the Penal Sum which is original k amt

Term
A third party beneficiary relationship that is incidental is sufficient to establish rights of recovery.
Definition

False, an intended third party beneficiary relationship will establish rights of recovery

 

p 19-20

Term
What does Right to work state mean? Is TN a right to work state?
Definition

This gives employees the power to decide for themselves whether they want to join or financially support a union

 

TN is a right to work state

Term
lien laws- who can file? how long does it last?
Definition

state and federal laws that ensure that people providing labor or materials for construction projects receive payment

 

a subcontractor on a residential project where GC has contract with owner cannot file a lien

 

lien lasts 1 year after work is finished in TN- must file it within 90 days

Term
Thomas & Associates v. Metro Government of Nashville
Definition

- No damages for delay clause- means there is only a time extension for delays- no $

 

-Courts are split on this issue and usually do not enforce it if delay was directly from owner actively interfering

 

-This case ruled in favor of owner (Metro)

 

 

Term

Type I vs. Type II differing site conditions

-definition, steps after, & proof

Definition

Type I- something must be indicated in a certain way in the contract documents, and when encountered on site, found to be different- to claim contractor must show they relied on contract docs causing detriment

 

Type II- Something differs materially from conditions normally expected, must be of such an unusual nature that it could not have been predicted for that kind of project- must give notice to owner- forced to use additional $ due to condition

Term
McClain v. Kimbrough
Definition

-Gives ruling that you cannot terminate without giving notice

 

-McClain was brick mason and when Kimbrough wasn't happy with mcclain's work, he went and hired another brick mason without telling McClain and breached contract

Term
Privity of Contract
Definition
the existence of a contractual relationship- must demonstrate this before seeking damages in a lawsuit
Term
Non enforceable Contracts- What constitutes? Examples?
Definition

-Not legally enforceable if contract contemplates illegal activity, contrary to public policy, not executed by authorized person

 

-Example is an unlicensed contractor performing work

Term
"Door Slamming" Policy- Is it enforced in TN?
Definition

-dealing with the enforceability of a contract by an unlicensed contractor

 

-this policy says the contract is null and void, can't seek relief in court

 

-TN stops short of door slamming- allows recovery of documented expenses with convincing proof- no recovery of profits

 

-if contractor exceeds its limit, it is considered contracting without license- 10% allowance

Term
Cost plus percentage fee contract- payment, when is it used, incentive?
Definition

-Cost Plus- Owner reimburses contractor for work and then there is a fee that is stipulated in contract

 

-Actual costs plus 10% fee

 

-used when plans and specs are incomplete

 

-no incentive to control costs- good idea to hire CM

 

 

Term
GMP Contract- when is it used?
Definition

-cost reibursable- cost of services + fee + contingency

 

-no payment givent to contractor over the GMP, owner keeps any savings if under the GMP

 

-plans and specs must be complete

Term
Cost Plus Fixed Fee, when is it used, fee
Definition

-reimburse actual cost plus a fixed fee determined as percentage of probable costs

 

-cost overrun no benefit to contractor

 

-used when plans and specs prohibit firm pricing

Term
Cost plus incentive fee contract
Definition

-cost reimbursable where fee is based on most probable cost

 

-owner and contractor split overrun/savings 50/50

Term
Competitive Bid/Lump sum contract- payment? risk?
Definition

-not cost reimbursable (meaning its fixed price)

 

-contractor paid an agreed fixed price paid on a pro-rata (proportionate) basis based on % of completion

 

- Contractor assumes all the risk (but gets all the savings if under budget)

Term
Schedule of Bid or Unit Price contract- kind of work where this is common
Definition

-Usually limited to narrow scopes of work- utilities, earthwork

 

-estimated quantities with a fixed unit price

 

-payment depends on quantity of work performed during pay period

Term
Spearine Doctrine
Definition

-Spearine performed work on a sewer exactly according to plans and specs- it is implied that the plans will be correct

 

-flood destroyed the sewer, but Spearine not responsible

 

-Ruling that contractors are not responsible for defects in plans and specs

Term
Docs that usually comprise a construction contract
Definition
-Bid documents, Integration/Merger (merges all prior negotiations into written contract), Plans and specs, general conditions, special conditions, addenda, surveys/geotech reports (physical conditions)
Term
Common Red Flag Clauses (8)
Definition
Dispute resolution, governing law, changes, differing site conditions, delays & suspensions, termination, notice exculpatory
Term
Red Flag Clause: dispute resolution- time, procedure, sovereign immunity
Definition

- general: precisely what steps the owner and contractor are required to take to resolve disputes

 

-Time limits- 21 days after occurence

 

-Procedural steps to follow -who is the initial decision maker (architect unless noted otherwise) -whether after there is mediation/arbitration/court

 

-steps to appeal decision

 

-sovereign immunity- meaning that contractor cannot sue in state court of law- must go to claims court run by the state and there is no appeal

 

Term

Red flag clause: Governing Law/Venue

 

TN Statute on governing law?

Definition

-Venue- location of action

 

-Governing law- which state law applies - law of project location or location of architect's place of business?

 

-TN statute- if the project is located in TN, laws of TN are applied clause saying otherwise is void

Term
Red flag clause: changes
Definition

-General: right of owner to change the contract unilaterally, places limitations on that right, contractor's duty to perform change (construction change directive), and contractor's right to be paid for performing change

 

- also architect has a right to change (minor)

Term
red flag clause: Differing site conditions- limits, who determines, special case
Definition

- Note the time limits

 

-the architect is to determine first

 

-applies to Type I and Type II site conditions

 

-article to suspend work if any human remains or archaeological sites are found

Term
red flag clause: Delays & suspensions
Definition

- excused or unexcused delay

 

- compensable or non-compensable

 

- Fed contract provisions are typically fair on delays beyond contractors control like acts of god and owner interference

 

-watch out for no damage for delay clause

Term
Red flag clause: terminations- types, examples, notice 
Definition

-Termination for cause - examples: fails to provide sufficient labor, fails to pay subs, substantial breach of contract

 

-Must give written notice and opportunity to cure (A201 =7 days written notice)

 

-Take work over- owner completes work and back charges the contractor

 

-Also termination for convenience clause

Term
Red Flag clause: Time (Notice), NTP, special case
Definition

-Notice To Proceed- when they can start, where they can work, number of days to complete work

 

-delayed NTP causes contractor resource allocation problem

 

-"time is of the essence" - must have these exact words

Term
Liquidated damages- what does it take to enforce? In TN? if contract is silent?
Definition

- no proof of actual damage required

 

-not enforceable in some states- Enforced in TN if reasonable and not a penalty

 

-if there is no liquidated damage provision, owner can try to prove actual damages due to late completion

Term
Moore v. Clarksville Case- One issue plus change order
Definition

Issue of site availability

 

-Implied obligations:

-to timely make worksite available w/o restrictions

 

-not to interfere, hinder, or delay performance

 

-watch out for limitation on work time or restricted use of work site

 

-Moore was awarded for delays of no fault of its own- delays were bc co-prime contractor occupied site

 

-also written change order requirement waived in this case

Term
Retention- what is it and its purpose? how much in TN
Definition

-contract funds held by owner until satisfactory completion and acceptance of work

 

-5% of each progress payment in TN

 

- purpose is to create a fund to fix defective work or contract default

Term
Red flag clause: Exculpatory clauses - examples, do courts enforce?
Definition

- relieves a party of liability

 

-Examples: indemnification, no damages for delay, limitation of liability

 

-many courts are reluctant to enforce them because they are unecessarily harsh

Term

Worker's comp-

 

- if sub fails to get WC

Definition

- required by statute covering the liability of employees getting hurt on the job

 

-employee cannot sue (tort suit) if company has worker's comp

 

-required by law no matter how many employees a contractor has

 

-if a sub fails to get worker's comp, then higher tier contractor will be responsible

Term

Comprehensive General Liability (CGL) Policy

- who obtains, what is it for, what triggers it

 

-what case?

Definition

- the contractor obtains and pays premiums for the CGL

 

-it protects them from claims for personal injury or property damage by third parties resulting from defective workmanship

 

-triggered by an "occurrence"- meaning an accident resulting in injury that was not expected

 

-travelers v. moore - court held that there was an "occurence" and that travelers must defend moore

Term

Builder's risk- Insurance

 

-who obtains, what is it for, how much is coverage worth

 

-named peril vs. all risk

Definition

-owner will obtain

 

-protects against loss by an external cause (basically an act of god

 

-coverage is for value of work lost up to limit of policy

 

-named peril is specific things like fire, flood, etc

 

-all risk covers everything (except exclusions- review these exclusions!)

Term

Errors & Omissions (E & O) Insurance

 

-who obtains, what is it

Definition

-designers/engineers obtain this insurance

 

-Insurance that covers professional negligence of design professionals

Term

Insurance Red Flags:

 

Endorsements

 

Deductible

 

subrogation

 

waiver of subrogation

Definition

endorsement- expand coverage to include more things

 

deductible- amount insured pays out of pocket before policy kicks in

 

subrogation- when insurance company pays loss, and then tries to recover that money if they think someone was at fault (subs)

 

-waiver- prevents insurance company from getting back losses

Term

Performance bond

-what is it for, what triggers coverage, principal & obligee

Definition

-to ensure that the work is completed

 

-triggered by principal's (contractor) default- surety is obligated to make sure the work is completed in this case if the obligee (owner) has not breached contract

Term

Surety

-response to default, options after

Definition

-response- perform investigation- determine whether principal is truly in default & obligee breached contract

 

options- assist to remedy default, take control and hire another contractor, let owner complete the project by hiring another contractor then paying them excess costs

 

Term

Payment Bonds

-whats it for, who requires,  (Little) Miller Act

Definition

-surety of this bond guarantees payment to third parties- which protects private owner from lien claims

 

-the owner requires

 

-Miller Act makes payment bond mandatory on Fed gov. projects greater than $100K- little requires a payment bond on any public works project and state highway projects in TN

Term
Express vs. Implied terms/obligations
Definition

express- things that are explicitly stated in contract- strong wordings like must, shall

 

implied- not explicitly stated but implied- things like good faith and fair dealing (subjective) and implied good workmanship- no implications if express term says otherwise

Term

Formal written requirement for change orders?

-cardinal change?

Definition

-courts like the written requirement- definite understanding between parties, avoids controversies

 

-written requirement can be waived by conduct or course of dealing by both parties- once waived, cannot be revoked

 

-cardinal change is a drastic change in the scope- excessive small changes may be cardinal

 

Term
Construction Acceleration- types, impacts
Definition

-voluntary acceleration- contractor chooses to accelerate- they have the burden of finishing on time, or want to finish early for incentive

 

-directed by owner- can't direct acceleration unless contract says so- if directed must compensate contractor

 

impacts- increased labor force, additional equip and material, resequencing, less efficient work, safety issues

Term
Measured Mile Method (acceleration)-proving indirect costs - other method
Definition

- production increased for known documented reason

 

-measure productivity over non-accel period and then measure productivity over accelerated period

 

- compare periods and interpolate accel costs - gives low and high estimate of total man hours- productivity loss

 

other method- total cost method- contractor claims 140% of contract and asks to get paid 40%- some courts do not accept

Term
Contract Claim essentials - proving claim, notice & time
Definition

- short descripition of claim

 

-contract provisions claim is based off of

 

-detailed desc. of extra work required and why

 

-prove claim with detailed documentation

 

- claim requires written notice that is within time limit

Supporting users have an ad free experience!