Shared Flashcard Set

Details

ISQS 4350
Practice Test 1
62
Computer Science
Undergraduate 4
01/31/2010

Additional Computer Science Flashcards

 


 

Cards

Term
1. The _________ for a project is the timetable that specifies when each activity should start and finish, and is usually represented by a Gantt Chart.
a. objective
b. schedule
c. scope
d. cost
Definition
b. Schedule
Term
2. It is important to develop a ________ before the start of the project; this _______ should include all the work tasks, associated costs, and estimates of the time necessary to complete them.
a. panel
b. plan
c. object list
d. time frame
Definition
b. Plan
Term
3. Ultimately, the responsibility of the project manager is to:
a. finish the project as quickly as possible
b. finish the project as cheaply as possible
c. make sure the customer is satisfied
d. make independent decisions
Definition
c. Make sure the customer is satisfied
Term
4. According to Burns, there are three major components to the life cycle of any IT project. They are:
a. schedule, execute and terminate
b. definition, planning and execution
c. scope, duration and cost
d. identification, incubation and resolution
Definition
b. definition, planning and execution
Term
5. A ________________ is a hierarchical tree of tasks to be undertaken by the project team during the project.
a. work load structure
b. project breakdown diagram
c. work breakdown structure
d. project task distribution list
Definition
c. Work breakdown structure
Term
6. A __________ diagram shows the necessary sequence and interdependencies of activities to achieve the project objective.
a. netting
b. breakdown
c. time-line
d. PERT network
Definition
d. PERT network
Term
7. The key to effective ____________ is measuring actual progress and comparing it to planned progress on a timely and regular basis and taking corrective action immediately, if necessary.
a. project planning
b. work breakdown
c. project control
d. quality efficiency
Definition
c. Project control
Term
8. Typically, an RFP is most like what other technical document usually produced in conjunction with software development projects?
a. Project plan
b. requirements document
c. functional specifications
d. feasibility study
e. contract
Definition
b. Requirements document
Term
9.The four phases of assembling teams are, in order:
a. forming, storming, norming, performing
b. storming, performing, norming, forming
c. norming, performing, forming, storming
d. forming, performing, storming, norming
e. none of these
Definition
a. Forming, storming, norming, performing
Term
10. The book The Fifth Discipline was authored by _______.
a. Stephen Covey
b. Eli Goldratt
c. Peter Singer
d. Peter Senge
e. Tom Peters
Definition
d. Peter Senge
Term
11. Which of the following is not one of the five disciplines?
a. personal mastery
b. mental models
c. shared vision
d. team learning
e. systemic processes
Definition
e. systemic processes
Term
12. The Seven Habits…. was authored by
a. Stephen Covey
b. Eli Goldratt
c. Peter Singer
d. Peter Senge
e. Tom Peters
Definition
a. Stephen Covey
Term
13. Which of the following is not one of the seven habits?
a. Be proactive
b. Network with managers
c. Begin with the end in mind
d. Think win/win
e. Synergize
Definition
b. Network with managers
Term
14. Which of the following is most useful for dealing (coping) with complexity?
a. The seven habits
b. Systems thinking
c. Theory of constraints
d. Project management
e. None of the above
Definition
b. Systems thinking
Term
15. In terms of managing one’s calendar, it is important to _____.
a. do planning and scheduling once a week
b. do planning and scheduling once a month
c. put the important activities on your calendar first
d. all of the above
e. a and c only
Definition
e. a and c only
Term
16. Good goal statements should
a. be measurable
b. begin with the infinitive To
c. have a target date
d. all of the above
e. a and c only
Definition
d. all of the above
Term
17. Goal setting is important because
a. It sets a direction for our lives
b. It programs our success mechanism
c. It causes us to focus on the future
d. All of the above
e. A and b only
Definition
d. All of the above
Term
18. To establish vision and mission statements, we need to ____.
a. determine our values
b. determine what we really enjoy doing
c. determine what is needed within our domain of influence
d. All of the above
e. B and c only
Definition
d. All of the above
Term
19. Milestones are ____ and usually occur at the _____
a. time consuming, end of a major phase
b. events, end of a small task
c. events, end of a major phase
d. time consuming, end of a small task
Definition
c. events, end of a major phase
Term
24. The work breakdown structure exhibits ___ whereas the Pert chart exhibits ____.
a. subordination, precedence
b. time-phasing, subordination
c. time-phasing, precedence
d. precedence, subordination
e. precedence, time-phasing
Definition
a. subordination, precedence
Term
25. The Gantt chart view indicates ___ of activities.
a. time-phasing
b. subordination
c. precedence
d. all of the above
e. none of the above
Definition
a. time-phasing
Term
30. Customers and competition place pressures on firms to ___
a. integrate with suppliers
b. shorten cycle times
c. improve quailty
d. lower costs
e. all of the above
Definition
e. all of the above
Term
31. According to chapter 1 of your copy packet, project management is frequently _____ .
a. competence management
b. fire-fighting management
c. risk management
d. product management
e. conventional management
Definition
c. risk management
Term
32. When considering personal vision, goals and activities, which should we determine first?
a. goals
b. vision
c. activities
Definition
b. vision
Term
33. When considering overall goals, why goals, what goals or how goals, which supports the what goals?
a. Overall goals
b. Why goals
c. How goals
d. None of these
e. A and b only
Definition
c. How goals
Term
34. The pictures, concepts people carry in their minds of themselves, their firms, their competition, even their customers are called _____.
a. shared visions
b. personal mastery
c. mental models
d. professional excellence
e. team learning
Definition
c. mental models
Term
35. Southwest Airlines is an example of a firm whose employees have a deep sense of _______
a. shared vision
b. personal mastery
c. mental model
d. professional excellence
e. team learning
Definition
a. shared vision
Term
36. Mental models are important because ____.
a. they are not readily perceived or understood
b. frequently, they are incorrect
c. they influence the decisions and actions taken
d. none of the above
Definition
c. they influence the decisions and actions taken
Term
37. Project managers do all but which of the following:
a. Provide intense leadership
b. Provide technical direction
c. Do some coaching, mentoring
d. Keep all parties informed
e. Do some negotiating
Definition
b. Provide technical direction
Term
38. Which of the following people groups is not one that the project manager has to deal with constantly? (recall Figure 3.3 in your copy packet)
a. suppliers
b. customers
c. upper management
d. line management
e. team members
Definition
a. suppliers
Term
39. ________________ contracts are most appropriate for projects that involve risk.
a. Fixed price
b. Flat price
c. Time and profit
e. Cost reimbursement
Definition
e. Cost reimbursement
Term
40. Which of the following is not a critical success factor of a project?
a. clearly defined goals and project mission
b. top management support
c. a competent project manager and team
d. a passive, complacent customer
e. sufficient resources
Definition
d. a passive, complacent customer
Term
41. Typical overall success rates for IT projects in the United States during the 1990’s was less than____ according to two studies performed by the Standish group
a. 28.3%
b. 45.6%
c. 53.5%
d. 66.2%
e. none of the above
Definition
a. 28.3%
Term
42. To effectively handle complex situations, project managers need to take a ____ view of a project and understand how it is situated within the larger organization.
a. myopic
b. jaundiced
c. holistic
d. narrow
e. none of the above
Definition
c. holistic
Term
43. _____ are sets of interacting components working within an environment with a common purpose.
a. Arrays
b. Systems
c. Problems
d. Models
Definition
b. Systems
Term
44. A project _____ is a collection of project phases.
a. lifecycle
b. manager
c. team
d. cost
e. none of the above
Definition
a. lifecycle
Term
45. According to Schwalbe, there are four major phases to a project. Which of the following is not one of the four phases?
a. concept
b. development
c. construction
d. implementation
e. close-out
Definition
c. construction
Term
46. According to Schwalbe, in the _____ phase, the project team creates a more detailed project plan, a more accurate cost estimate, and a more thorough WBS. Use the same list as above.
a. concept
b. development
c. construction
d. implementation
e. close-out
Definition
b. development
Term
47. According to Schwalbe, in the ____ phase the project team delivers the required work. The bulk of a project team's effort and the most money are usually spent during this phase. Use the same list as above.
a. concept
b. development
c. construction
d. implementation
e. close-out
Definition
d. implementation
Term
48. The spiral model for software development was invented by ______.
a. Eli Goldratt
b. Barry Boehm
c. Peter Senge
d. Tom Peters
Definition
b. Barry Boehm
Term
49. Common names for the phases of the SDLC are, according to Schwalbe, all but _____.
a. information systems planning
b. analysis
c. design
d. implementation
e. testing
Definition
a. information systems planning
Term
50. Many large information technology projects are developed as a series of _______.
a. phases
b. processes
c. projects
d. milestones
Definition
c. projects
Term
51. Organizations can be viewed as having four different frames. Which of the following is not one of the four frames?
a. structural frame
b. human resources frame
c. political frame
d. creativity frame
e. symbolic frame
Definition
d. creativity frame
Term
52. Which of the following is not one of the general classifications of organizational structures described by Schwalbe?
a. functional
b. project
c. matrix
d. product
Definition
d. product
Term
53. In which of the above do personnel report to both a functional (line) manager and to one or more project managers? {Use the same list as above.}
a. functional
b. project
c. matrix
d. product
Definition
c. matrix
Term
54. In which of the above do project managers have the greatest authority? {Use the same list as above.}
a. functional
b. project
c. matrix
d. product
Definition
b. project
Term
55. How important is user involvement in the overall success of a project, according to the Standish group CHAOS 1995 report?
a. not important
b. somewhat important
c. very important
Definition
c. very important
Term
56. Project _____ ______ includes the processes involved in coordinating all of the other project management knowledge areas through a project’s life cycle.
a. scope management
b. integration management
c. time management
d. resource management
e. cost management
Definition
b. integration management
Term
57. Project _____ ______ includes the processes involved in defining and controlling what is or is not included in a project. {Use the same list as above.}
a. scope management
b. integration management
c. time management
d. resource management
e. cost management
Definition
a. scope management
Term
58. Strategic planning and project selection are part of project _____ ______. {Use the same list as above.}
a. scope management
b. integration management
c. time management
d. resource management
e. cost management
Definition
a. scope management
Term
59. Net present value approaches to project selection are difficult because _____.
a. NPV calculations are often incorrect
b. The discount rate is unknown, in reality
c. Mapping future cash flows back to the present is impossible.
d. The probable future savings or revenues that will accrue the project are unknown.
Definition
d. The probable future savings or revenues that will accrue the project are unknown
Term
60. A _____ ______ is a document that formally recognizes the existence of a project and provides direction on the project’s objectives.
a. functional specification
b. project plan
c. project charter
d. statement of work
e. none of the above
Definition
a. functional specification
Term
61. Which construct is used in conjunction with project scope definition and management?
a. WBS
b. Gantt
c. Resource charts
d. Pert
Definition
a. WBS
Term
62. Which construct is used in conjunction with project time management? {Use the same list as above.}
a. WBS
b. Gantt
c. Resource charts
d. Pert
Definition
b. and d. Gantt and Pert
Term
63. The tendency of a project to keep getting bigger and bigger is referred to as ____ _____.
a. feature creep
b. hope creep
c. scope creep
d. cope creep
e. none of these
Definition
c. scope creep
Term
64. Schwalbe suggests a number of approaches to developing work breakdown structures. Which of the following is not one of the ways
a. Using guidelines
b. Analogy approach
c. Case-based approach
d. Top-Down approach
e. Bottom-up approach
Definition
c. Case-based approach
Term
65. Formal acceptance of the scope definition by the project stakeholders is called _____ _____.
a. Scope verification
b. Scope initiation
c. Scope planning
d. Scope change control
Definition
a. Scope verification
Term
66. Amongst network diagrams, which of the following is preferred and most used within PM software packages?
a. Activity-on-arrow diagram
b. Activity-in-box diagram
c. precedence diagramming method
d. none of the above
e. both b and c
Definition
b. Activity-in-box diagram
Term
67. There are four types of dependencies or relationships between activities. Which of the four is the least used?
a. Finish-to-start
b. Start-to-start
c. Finish-to-finish
d. Start-to-finish
Definition
d. Start-to-finish
Term
68. Of the above dependency types which is most used and the default linkage assumed by MS Project? {Use the same list as above.}
a. Finish-to-start
b. Start-to-start
c. Finish-to-finish
d. Start-to-finish
Definition
a. Finish-to-start
Term
69. Sources of information regarding the duration of project activities include:
a. the persons who are assigned to those activities
b. history database of activity durations for activities of similar types
c. the use of formulas
d. all of the above
Definition
d. all of the above
Term
70. Before a project plan can be compared to actual durations, start and stop dates, the plan must be
a. Baselined
b. Frozen
c. Approved
d. Stored
e. Validated
Definition
a. Baselined
Supporting users have an ad free experience!