Term
AIA - five documents related to interior design work |
|
Definition
1. A175 ID Standard form of agreement between owner and vendor for FFE where the basis of payment is stipulated sum 2. A275 ID General conditions of the contract for furniture, furnishings and equipment 3. A775 ID invitation and instructions for quotation of FFE 4. B171 ID Standadard form of agreement between owner and architect for architectural interior design services 5. B175 ID Standard form of agreement between owner and architect for FFE design services |
|
|
Term
contract documents consist of: |
|
Definition
owner-contractor agreement general conditions of the contract supplementary conditions of the contract drawings specifications addenda modifications (change order) |
|
|
Term
|
Definition
typically cover only moviable items such as furniture, appliances, rugs, lamps & accessories
separate from construction contract because governed by law that regulates the sale of goods rather than services |
|
|
Term
major provisions of A175 ID |
|
Definition
1. identification of contract documents (agreement, conditions, drawings, specs, schedules, addenda, etc, and refers to later section with all are listed in detail) 2. basic provisions - description of work, time of commencement and completion and the contract sum, describes scope, compensation 3. progress payments - net days from approval of pay app, criteria for payment, restocking, final payment, based on percentage complete and materials purchased, retainage of 10% 4. 4. |
|
|
Term
|
Definition
the stage in the progess of the work when the work is sufficiently complete according to the contract documents so that the owner can occupy or utilize the site |
|
|
Term
|
Definition
money's paid to the owner for every day the project is late, represent actual anticipated losses the owner will incur (eg, rent) |
|
|
Term
|
Definition
must include both if included in contract, an incentive to complete the project on time and does not have to have a relationship to actual monetary losses |
|
|
Term
|
Definition
incorporated by specific reference into the owner-designer agreement and the owner-vendor agreement
coordinated with UCC (uniform commercial code) governing the sale of goods |
|
|
Term
|
Definition
free on board, followed by factory or destination, means the title is transferred at the factory or destination |
|
|
Term
|
Definition
1. provide area vendor can use to do work 2. access to premises at reasonable times 3. provide space for receipt, inspection, and staging of materials 4. provide temporary utilities, facilities necessary 5. provide normal security for the premises
conduct an acceptance inspection and notify the vendor in writing |
|
|
Term
|
Definition
ordering, delivering, and installing goods typically warehouses the goods visit the project site and review the contract documents prepare purchase orders supervise the work,pay for labor, materials, ff& e, and other facilities necessary schedule provide for final clean up |
|
|
Term
|
Definition
vendor has the risk of loss of the furniture until owner accepts it after final inspection or upon payment in full, whichever happens first |
|
|
Term
|
Definition
the dentention of a shipment in port/train/boat by ship owner beyond normal or agreed upon term
gives extra time to vendor to complete work since this is out of their control |
|
|
Term
responsibility of interior designer in construction |
|
Definition
act as owner's representative assists in coordinating schedules site visits and keeps owner informed recommends whether work should be rejected does not have authority to reject or stop work, or terminate contract on behalf of the owner review shop drawings and submittals to check conformance prepare change orders authorize minor changes final inspection |
|
|
Term
responsibility of owner in construction |
|
Definition
furnish evidence that finances have been set up provide surveys describing physical characteristics of site owner can stop work if contractor persistently fails to carry out work notify the gc in writing of items to correct - gc has 7 days, 2nd notice, 7 days, then owner can correct on his own and deduct from gc contract |
|
|
Term
responsibilites of contractor during construction |
|
Definition
soley responsible for all fabrication, delivery, and installation means, methods, techniques and procedures, and for coordinating all portions of the work visiting the site and taking any measurements necessary responsible for all act and omissions of subs notify designer of variances or assumes all responsibility of said issue provide a schedule and keep it current, and cooperation with owner and designer in coordinating the schedules of other contractors idemnification - hold the owner and designers harmless in the result of injury or property damage due to performance of work |
|
|
Term
supplementary conditions of the contract - general categories (4) |
|
Definition
1. bidding 2. contractual matters between owner-contractor 3. modification of general conditions 4. modification of division 01, general requirements of the specifications |
|
|
Term
additional optional info in the supplementary conditions |
|
Definition
permission to submit info in digital form additional info cost of architect to review requests for substitutions provisions for the owner to pay for utilities requirements that the contractor employ a superindent provisions for fast track scheduling reimbursement by contractor for extra site visits by architect due to contractor fault protection for the owner against claims for additional time requirements for more detailed information on costs and overhead requirements for liquidated damages or penalty's/bonuses bonding/insurance |
|
|