Defense Resource Allocation: PPBE
Week 7
17
Business
Graduate
02/23/2014

Additional Business Flashcards

 


 

Cards

Term
What is the PPBE process?
Definition
Articulates Strategy
Identifies size, structure & equipment for military forces
Sets programming priorities
Allocates resources
Evaluates actual output against planned performance & adjusts resources as appropriate
Term
Four phases of PPBE?
Definition
Planning
Programming
Budgeting
Execution
Term
What is the question being answered & purpose of the PPBE's Planning phase?
Definition
Q: What capabilities are required?
P: Provide overall guidance for resource allocation
Term
What is the question being answered & purpose of the PPBE's Programming phase?
Definition
Q: Which programs best meet the military strategy?
P: Allocate resources to support SPG/JPG goals
Term
What is the question being answered & purpose of the PPBE's Budgeting phase?
Definition
Q: Are programs within fiscal policy?
P: Prepare a defensible budget.
Term
What is the question being answered & purpose of the PPBE's Execution phase?
Definition
Q: Are we executing efficiently?
P: Provide feedback
Term
POM
Definition
Program Objectives Memorandum
Principal planning document addressing DoD requirements over the FTDP. A fiscally constrained memo from the Components to OSD which recommends a balanced allocation of resources, programs, & manpower
Term
BES
Definition
Budget Estimate Submission.
The DoD Component's budget submissions to OSD showing budget requirements for inclusion in the DoD budget.
Term
Contrast POM vs BES
Definition
6yr vs 2 yr
MFP/component vs. appropriation
Term
The purpose of the PPBE process from an OSD perspective
Definition
Balance Requirements to available resources
-Accommodate Topline Resource Changes
-Readiness vs. Modernization
Address Admin/DoD Priorities
-National Programs
-Strategic Planning Guidance (SPG) & Joint Planning Guidance (JPG)
-Programming Decisions (PDM)
Acquisition Initiatives
-Acquisition Reforms
-ADM/Baseline Conformity
-Industrial Base Concerns
Assure Joint Programs are Consistent
Budget "Scrub" Issues
-Pricing/Phasing/Budget Policy/Execution
-Economic Indices/PAy Raises
-Outlay Projections
Term
The purpose of the PPBE Process from the PM's perspective
Definition
Out Year Funding
-Know your funding needs by year and Appropriation ("Color")
-Ensure FTDP accurately reflects your needs
POM Funding
-Ensure POM Build is accurate
-Know impacts of funding cuts through risk management
-Know when funding changes are likely and be prepared to accurately respond to reduced funding level proposals/direction
Budget Execution
-Execute efficiently, watch obligation rates - 4th Qtr critical!
-Know rules for reprogramming and trading colors of funding
-Schedule contract awards away from 4th Qtr
Be prepared to execute additional, short fused funding
Term
4 Primary reasons why programs lose funding.
Definition
Scarcity or Resources
Questionable need for program
Risk
Funding / Execution Issues
Bonus: Politics
Term
What are the major products of the PPBE process?
Definition
Strategic Planning Guidance
Joint Programming Guidance
POM
BES
President's Budget (PB)
Term
What is the goal of PPBE?
Definition
Buy the National Security Strategy in a politically viable fashion
Term
PPBE Overview
Definition
Plan a National Strategy
Program the hardware, skils, etc needed
Budget to fund the approved programs
Execute the program and ensure they achieve the national strategy
Term
JPG
Definition
Joint Planning Guidance
JPG – is the principle DoD planning document and reflects the President’s prioritized national security objectives drawn from the National Security Strategy, National Military Strategy, and the QDR.
Term
"Train Wreck"
Definition
When the JPG gets sent to the Comptroller and they do not have the money to support it