Term
|
Definition
When a resource works on more than one task at a time |
|
|
Term
|
Definition
The amount of time an activity can be delayed without delaying a succeeding activity or the project finish date |
|
|
Term
|
Definition
This diagramming is more popular than ADM method. It is used by project management software activities are represented by boxes |
|
|
Term
|
Definition
A tabulation of activities to be included on a project schedule |
|
|
Term
|
Definition
People, equipment and materials" |
|
|
Term
|
Definition
A significant event that normally has no duration on a project; serves as a marker to help in identifying necessary activities, setting schedule goals, and monitoring progress |
|
|
Term
|
Definition
The amount of time an activity can be delayed from its early start without delaying the planned project finish date |
|
|
Term
|
Definition
A dependency where task B cannot finish until task A finishes |
|
|
Term
|
Definition
A scheduling method that considers limited resources when creating a project schedule and includes buffers to protect the project completion date |
|
|
Term
|
Definition
A network diagram where activities are represented by arrows |
|
|
Term
|
Definition
The latest possible time an activity can start based on the project network logic |
|
|
Term
|
Definition
A management philosophy developed by Eliyahu M. Goldratt and introduced in his book The Goal |
|
|
Term
|
Definition
The amount of time a project activity may be delayed without delaying a succeeding activity or the proeject finish date |
|
|
Term
|
Definition
These dependencies are inherent in the nature of the work being performed on a project; sometimes referred to as hard logic |
|
|
Term
|
Definition
The number of workdays or work hours required to complete a task |
|
|
Term
|
Definition
The longest path through the network diagram that has the least amount of slack or float |
|
|
Term
|
Definition
Dependencies that involve relationships between project and non-project activities |
|
|
Term
|
Definition
A milestone activity that is completed later than planned |
|
|
Term
|
Definition
The approved planned schedule for the project |
|
|
Term
|
Definition
A dependency where task B cannot finish until task A starts |
|
|
Term
|
Definition
A schematic display of the logical relationships among, or sequencing of, project activities |
|
|
Term
|
Definition
A chart that provides a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar format |
|
|
Term
|
Definition
This type of buffer adds time before tasks on the critical path |
|
|
Term
|
Definition
This law states that if something can go wrong, it will |
|
|
Term
|
Definition
A network diagramming technique used to predict total project duration |
|
|
Term
|
Definition
An element of work, normally found on the WBS, that has an expected duration and cost, and expected resource requirements |
|
|
Term
RESOURCE BREAKDOWN STRUCTURE |
|
Definition
A hierarchical structure that identifies the project's resources by category and type |
|
|
Term
|
Definition
An estimate that includes an optimistic, most likely, and pessimistic estimate |
|
|
Term
|
Definition
These provide more information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity |
|
|
Term
|
Definition
The processes required to ensure timely completion of a project |
|
|
Term
|
Definition
Criteria that help define milestones (smart, measurable, assignable, realistic, and time-framed) |
|
|
Term
|
Definition
This type of pass determines the late start and finish dates |
|
|
Term
|
Definition
The planned schedule dates for activities in a tracking gantt chart |
|
|
Term
|
Definition
This type of buffer adds time before the projects due date |
|
|
Term
|
Definition
The earliest possible time an activity can finish based on the project network logic |
|
|
Term
|
Definition
An element of work normally found on the WBS that has an expected duration, a cost, and resource requirements |
|
|
Term
|
Definition
Dependencies defined by the project team; sometimes referred to as soft logic and should be used with care because they may limit later scheduling options |
|
|
Term
|
Definition
Duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three-point estimate |
|
|
Term
|
Definition
The actual amount of time worked on an activity plus the elapsed time |
|
|
Term
|
Definition
A dependency where task B cannot start until task A starts |
|
|
Term
|
Definition
When a single node is followed by two or more activities in a network diagram |
|
|
Term
|
Definition
The starting and ending point of an activity on an activity-on-arrow diagram |
|
|
Term
|
Definition
The earliest possible time an activity can start based on the project network logic |
|
|
Term
|
Definition
When two or more nodes precede a single node on a network diagram |
|
|
Term
|
Definition
A pass through the network diagram that determines the early start and finish dates |
|
|
Term
|
Definition
The amount of time an activity can be delayed without delaying the early start of any immediately following activities |
|
|
Term
|
Definition
The most common type of dependency |
|
|
Term
|
Definition
Law which states that work expands to fill the time allowed |
|
|
Term
|
Definition
A sequencing of project activities or tasks; also called a relationship |
|
|
Term
|
Definition
A chart that compares planned and actual project schedule information |
|
|
Term
|
Definition
Additional time to complete a task |
|
|
Term
|
Definition
The latest possible time an activity can finish based on the project network logic |
|
|
Term
|
Definition
A type of activity that has no duration and uses no resources but is used to show a logical relationship between two activities in the arrow diagramming method of project network diagrams |
|
|
Term
|
Definition
This technique shortens project schedules by doing activities in parallel or overlapping them |
|
|
Term
|
Definition
A project network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates |
|
|
Term
|
Definition
A technique for making cost and schedule tradeoffs to obtain the greatest amount of schedule compression for the least incremental cost |
|
|