Term
|
Definition
conditions that must be met before deliverables are accepted |
|
|
Term
|
Definition
distinct scheduled portion of work performed during a project |
|
|
Term
|
Definition
Cost incurred for the work performed on a activity during a specific time |
|
|
Term
|
Definition
estimating the duration or cost of an activity/project using historical data from similar project |
|
|
Term
|
Definition
effort is allotted proportionately across certain discrete efforts not divisible discrete efforts. Used for EVM (Earned Value Management) |
|
|
Term
|
Definition
factor in planning process that is considered to be true, real, or certain, without proof or demonstration |
|
|
Term
|
Definition
critical path method technique for calculating late start and late finish. Work from end to start of model |
|
|
Term
|
Definition
Approved version of a work product that can only be changed through formal change control and used as a basis for comparison |
|
|
Term
|
Definition
method of estimating project cost or duration by adding the estimates of lower level components of the WBS |
|
|
Term
|
Definition
sum of all budgets established for the work to be performed |
|
|
Term
|
Definition
process where modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected. |
|
|
Term
|
Definition
form group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project. Used to record and communicate such decisions |
|
|
Term
|
Definition
formal proposal to modify any document, deliverable, or baseline |
|
|
Term
|
Definition
numbering system to uniquely identify each component of the work breakdown structure |
|
|
Term
Communications Management Plan |
|
Definition
describes how, when and by whom information will be administered and disseminated |
|
|
Term
|
Definition
limiting factor that affects execution |
|
|
Term
|
Definition
management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement |
|
|
Term
|
Definition
intentional activity that realigns the performance of the project work with the project management plan |
|
|
Term
|
Definition
describes how cost will be planned, structured, and controlled |
|
|
Term
|
Definition
measure of cost effciency of budgeted resources expressed as the ratio of earned value to actual cost |
|
|
Term
|
Definition
amount of budget deficet or surplus at a given point. Earned value - Actual cost |
|
|
Term
|
Definition
shortening the schedule duration for the least incremental cost by adding resources |
|
|
Term
|
Definition
schedule method that places buffers on project schedule path to account for limited resources and uncertainties |
|
|
Term
|
Definition
sequence of activities that represents the longest path through a project, which determines the shortest possible duration |
|
|
Term
|
Definition
any activity on the critical path schedule |
|
|
Term
|
Definition
used to estimate minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model |
|
|
Term
|
Definition
a point in time when the status of the project is recorded |
|
|
Term
|
Definition
Diagramming and calucation technique for evaluating the implications of a chain multiple options in the presence of uncertainty |
|
|
Term
|
Definition
technique to divide the project scope and project deliverables into smaller, more manageable parts |
|
|
Term
|
Definition
An intention activity to modify a nonconforming product or product component |
|
|
Term
|
Definition
any unique and verifable product, result, or capability to perform a service that is requried to be produced to complete a process, phase, or project |
|
|
Term
|
Definition
an activity that can be planned and measured and that yields a specific output. One of the EVM techniques |
|
|
Term
|
Definition
in critical path method, earliest possible time when uncompleted activity can finish |
|
|
Term
|
Definition
in critical path method, earliest possible point when uncompleted activities can start |
|
|
Term
|
Definition
measure of work performed expressed in terms of the budget authorized for the work |
|
|
Term
|
Definition
methodology that combines scope, schedule, and resource meaurements to asses project performance and progress |
|
|
Term
|
Definition
number of labor units required to complete a schedule activity or work breakdown structure component, expressed in hours or days |
|
|
Term
Enterprise Enviromental Factors |
|
Definition
conditions, not under the immediate control of the team, that influence, constrain, or direct the project |
|
|
Term
|
Definition
expected total cost of completing work expressed as sum of the actual cost to date and the estimate to complete |
|
|
Term
|
Definition
expected cost to finish all the remaining project work |
|
|
Term
|
Definition
schedule compression technique in which activities or phases normally done in sequence are performed in parallel |
|
|
Term
|
Definition
successor activity cannot finish until predecessor activity has finished |
|
|
Term
|
Definition
successor activity cannot start until predecessor activity finishes |
|
|
Term
|
Definition
critical path meth technique for calculating early start and early finish dates by working forward throught the schedule model from the project start |
|
|
Term
|
Definition
amount of time schedule activity can be delayed without delaying the early start date of successor |
|
|
Term
|
Definition
bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to start and finish dates |
|
|
Term
Human Resource Management Plan |
|
Definition
component of project management plan that describes how the roles and responsibilties, reporting relationships, and staff management will be addressed |
|
|
Term
|
Definition
amount of time a successor activity is required to be delayed with respect to the predecessor activity |
|
|
Term
|
Definition
in critical path method, latest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, project completion date, or schedule constraints |
|
|
Term
|
Definition
in critical path method, latest possible time when uncompleted activity can start based on the schedule |
|
|
Term
|
Definition
amount of time a successor activity can be advanced with respect to a predecessor activity |
|
|
Term
|
Definition
knowledge gained during project and how issues were addressed, improves future performance |
|
|
Term
|
Definition
activity that does not produce definitive end products and is measured by the passage of time. EVM technique |
|
|
Term
|
Definition
dependency betweek two activities or between an activity |
|
|
Term
|
Definition
|
|
Term
|
Definition
estimate of the most probable activity duration that takes into account all known variables that could affect performance |
|
|
Term
|
Definition
a risk that would have a positive effect on one or more project objectives |
|
|
Term
|
Definition
estimate of the shortest activity duration that takes into account all known variables that could affect performance |
|
|
Term
Organizational Breakdown Structure |
|
Definition
hierarchical representation of the project organization, which shows what project activities will be completed by what organizational groups |
|
|
Term
Organizational Process Assets |
|
Definition
Plans, processes, polocies, procedures, and knowledge bases specific to and used by the performing organization |
|
|
Term
Organizational Project Management Maturity |
|
Definition
level of organization's ability to deliver desired outcomes in reliable manner |
|
|
Term
|
Definition
estimating technique which an algorithm isued to calculate cost or duration based on historical data and project performance |
|
|
Term
|
Definition
relationship which schedule activity has more than one predecessor |
|
|
Term
|
Definition
relationship which schedule activity has more than one successor |
|
|
Term
|
Definition
estimate expressed as percent of work that has been completed on a WBS |
|
|
Term
|
Definition
enterprise whose personnel are the most directly involved in doing the work of the project |
|
|
Term
|
Definition
estimate of the longest activity duration |
|
|
Term
|
Definition
review at the end of a phase to determine if next phase should start. |
|
|
Term
|
Definition
authorized budget assigned to scheduled work |
|
|
Term
|
Definition
Projects, programs, and operations managed as a group to achieve strategic objectives |
|
|
Term
|
Definition
process of optimizing the mix of portfolio components to further the strategic objectives of the organization |
|
|
Term
|
Definition
certralized management of one or more portfolios to achieve strategic objectives |
|
|
Term
Precedence Diagramming Method |
|
Definition
technique used for constructing schedule model which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence the activites will be performed |
|
|
Term
|
Definition
activity that logically comes before dependent activity |
|
|
Term
|
Definition
intentional activity that ensures future performance of the project work is aligned with the project management plan |
|
|
Term
Probabilty and Impact Matrix |
|
Definition
grid for mapping the probability of each risk occurence and its impact on the project objectives |
|
|
Term
Procurement Management Plan |
|
Definition
describes how the team will acquire goods and services from outside the organization |
|
|
Term
|
Definition
series of phases that represent the evolution of a product , from concept through delivery, growth, maturity, and retirement |
|
|
Term
|
Definition
group of related projects that are managed together to create benefits that would be achieved if managed individually |
|
|
Term
|
Definition
application of knowledge, skills, tools, and techniques to a program to meet the program requirements. |
|
|
Term
Program Management Office |
|
Definition
standardizes program related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques |
|
|
Term
|
Definition
iterative process of increasing the level of detail in a project management plan as more information and accuracte estimates are available |
|
|
Term
|
Definition
temporary endevor undertaken to create unique product, service |
|
|
Term
|
Definition
calendar that identifies working days and shifts that are available for scheduled activites |
|
|
Term
|
Definition
Document issed by project sponser, formally authorizes project, gives project manager authority to apply organizational resources |
|
|
Term
|
Definition
series of project phases that a project passes through from its initiation to its closure |
|
|
Term
|
Definition
application of knowledge, skills, tools, and techniques to project activites to meet project requirements |
|
|
Term
Project Management Office |
|
Definition
standardized project related governance, facilitates sharing of resources |
|
|
Term
|
Definition
document that describes how the project will be executed, monitored, and controlled |
|
|
Term
|
Definition
person assigned to lead the team and is responsible for achieving project objectives |
|
|
Term
|
Definition
collection of logically related project activites that culminates in the completion of one or more deliverables |
|
|
Term
|
Definition
output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources |
|
|
Term
Project Schedule Network Diagram |
|
Definition
graphical representation of logical relationships among project schedule activities |
|
|
Term
|
Definition
work performed to deliver product, service, or result |
|
|
Term
|
Definition
describes how an organizations quality policies will be implemented |
|
|
Term
|
Definition
condition that is required to be present in a product, service, or result to satisfy a contract or other formally imposed specification |
|
|
Term
Requirements Management Plan |
|
Definition
describes how requirement will be analyzed, documented, and managed |
|
|
Term
Requirements Traceability Matrix |
|
Definition
grid that links product requirements from their orgin to the deliveables that satisfy them |
|
|
Term
Resource Breakdown Structure |
|
Definition
hierarchical representation of resources by category and type |
|
|
Term
|
Definition
identifies workingdays and shifts upon which each specfic resource available |
|
|
Term
|
Definition
technique which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply |
|
|
Term
Responsibilty Assignment Matrix |
|
Definition
grid that shows the project resources assigned to each work package |
|
|
Term
|
Definition
uncertain event that has either positive or negative effect |
|
|
Term
|
Definition
risk response strategy where the project team decides acknowledge the risk and not take any action if the risk occurs |
|
|
Term
|
Definition
risk response strategy, project team acts to eliminate the threat or protect the project from its impact |
|
|
Term
|
Definition
hierarchical representation of risks that is organized according to risk categories |
|
|
Term
|
Definition
group of potential causes of risk |
|
|
Term
|
Definition
component of the project, program, or portfolio management plan that describes how risk management activites will be structured and performed |
|
|
Term
|
Definition
Risk response strategy where the project team acts to reduce the probability of occurrence of a risk |
|
|
Term
|
Definition
document which results of risk analysis and risk respons planning are recorded |
|
|
Term
|
Definition
risk response strategy, the project team shifts the impact to a third party, ownership together |
|
|
Term
|
Definition
iterative planning technique, work in near term is planned in detail, work in the future is planned at higher level |
|
|
Term
|
Definition
approved version of a schedule model that can be changed through formal change control and is the basis for comparison of actual results |
|
|
Term
|
Definition
technique used to shorten schedule duration without reducing scope |
|
|
Term
|
Definition
establishes criteria and the activities for developing, monitoring, controlling schedule |
|
|
Term
|
Definition
representation of the plan for executing the project activites, including durations, dependancies, and other planning information used to produce a schedule |
|
|
Term
|
Definition
process used to investigate or analyze the output of the schedule model in order to optimize the schedule |
|
|
Term
Schedule Performance Index |
|
Definition
measure of schedule efficiency expressed as the ratio of earned value to planned value
EV/PV |
|
|
Term
|
Definition
measure of schedule performance expressed as the difference between earned value and planned value
EV-PV |
|
|
Term
|
Definition
approved version of the scope statement, WBS, WBS dictionary, which can be changed only through change control. |
|
|
Term
|
Definition
uncontrolled expansion to product scope without adjustments in time, cost, or resources |
|
|
Term
|
Definition
describes how the scope will be defined, developed, monitored, controlled, and validated |
|
|
Term
|
Definition
earned value technique used to indicate performance trends by using graph that displays cumulative costs over a specific time period |
|
|
Term
|
Definition
risk that arises as a direct result of implementing a risk response |
|
|
Term
|
Definition
person or group that provides resources and support for the project, program, portfolio, and is accountable for enabling success |
|
|
Term
|
Definition
describes how team members will be acquired and how long they will be needed |
|
|
Term
|
Definition
individual, group, or organization that may affect, be affected by, or percieve itself affected by a outcome of a project |
|
|
Term
|
Definition
logical relationship, successor activity cannot finish until predecessor activity has started |
|
|
Term
|
Definition
dependent activity that logically comes after another activity in a schedule |
|
|
Term
|
Definition
risk that would have negative effect on project |
|
|
Term
|
Definition
technique used to estimate cost or duration by applying average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates |
|
|
Term
To Complete Performance Index |
|
Definition
measure of the cost performance that is require to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget |
|
|
Term
|
Definition
amount of time that a schedule activity can be delayed or extended from its early start with delaying the project finish date |
|
|
Term
|
Definition
event that indicates that a risk is about to occur |
|
|
Term
|
Definition
technique used for determining the cause and degree of difference between the baseline and actual performance |
|
|
Term
|
Definition
projection of the amount of budget deficit or surplus expressed as the difference between the budget at completion and the estimate at completion
BAC-EAC |
|
|
Term
|
Definition
document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure |
|
|
Term
What if Scenario Analysis |
|
Definition
process of evaluating scenarios in order to predict their effect on project objectives |
|
|
Term
|
Definition
hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create required deliverables |
|
|
Term
|
Definition
work defined at the lowest level of the WBS for which cost and duration can be estimated and managed |
|
|
Term
|
Definition
response to threat that has occurred for which was not planned for prior |
|
|