Term
What is the purpose of the 6th process in Project Schedule Management? |
|
Definition
To monitor status of project schedule to update schedule. Measures current schedule against baseline. Influence changes to schedule baseline. |
|
|
Term
What are the inputs for the 6th process in Project Schedule Management? |
|
Definition
1. PMP 2. Project Documents 3. Work Performance Data 4. OPAs |
|
|
Term
How do you use the 6th process in Project Schedule Management for an agile lifecycle? |
|
Definition
Determine status of completed work conduct retrospectives reprioritize remaining work Determine schedule has changed |
|
|
Term
What are the Tools and Techniques for the 6th process in Project Schedule Management? |
|
Definition
1. Data Analysis - Iteration burndown Charts, EV analysis 2. CPM 3. PMIS 4. Resource Optimization 5. Leads and Lags 6. Schedule Compression |
|
|
Term
What are the outputs for the 6th process in Project Schedule Management? |
|
Definition
1. Work Performance Information 2. Schedule Forecasts 3. Change Requests 4. PMP Updates 5. PD Updates |
|
|