Term
What is the purpose of Sequence Activities? |
|
Definition
To identify and document relationships/dependencies among activities |
|
|
Term
What are the inputs for the 3rd process in Project Schedule Management? |
|
Definition
1. PMP - Schedule MP, Scope Baseline 2. Project Documents -Outputs of Define Activities 3. EEFs 4. OPAs |
|
|
Term
What are the tools and techniques of the 3rd process in Project Schedule Management? |
|
Definition
1. PDM 2. DDI 3. Lead and Lags 4. PMIS |
|
|
Term
Explain the (PDM) for Project Schedule Management. Explain the four kinds of attributes. |
|
Definition
It is the Precedence Diagramming Method. It is a diagram that shows the relationships between activities. (FS)-Bake cake before decorating (FF)-Delivering the cake can't happen until it is decorated (SS)-You can preheat the oven while mixing the batter (SF)-New oven has to come in before you replace old one. |
|
|
Term
Explain (DDI) for Project Schedule Management |
|
Definition
Dependency Determination and Integration 1. Mandatory Dependency 2. Discretionary Dependency 3. External Dependency 4. Internal Dependency |
|
|
Term
What are the outputs for the 3rd process in Project Schedule Management? |
|
Definition
1. Project Schedule Network Diagrams (Network Diagrams) 2. Project Documents Updates |
|
|
Term
What are the mathematical symbols for lead and lag? |
|
Definition
|
|