Term
What is the purpose of the 6th process in Project Scope Management? How and why? Diverts? |
|
Definition
To Monitor the scope and control changes to scope baseline. Done by measuring work performance data and comparing to scope baseline. Allows for preventative and corrective action.
Diverts changes to perform integrated change control process |
|
|
Term
What are the inputs for the 6th process in Project Scope Management? |
|
Definition
1. PMP-SMP,RMP 2. Project Documents - RTM, Requirement Docs, Scope Baseline, Quality reports, 3. Work performance Data 4. OPAs |
|
|
Term
What are the Tools and Techniques for the 6th process in Project Scope management? |
|
Definition
1. Data Analysis -Variance Analysis, Trends Analysis |
|
|
Term
What are the Outputs for the 6th process in Project Scope Management? |
|
Definition
1. PMP updates 2. Change Requests 3. Work Performance Information 4. Project Documents Updates |
|
|