Term
What are the inputs for the 1st process in Integration Management? |
|
Definition
1. Business Documents 2. Agreements 3. EEFs 4. OPAs |
|
|
Term
What is the purpose of the Project Charter? |
|
Definition
To authorize existence of project. Provide high level summary of project description, requirements, PM assignment/authority, Schedule summary, and business case (why). |
|
|
Term
What are the Tools and Techniques for the 1st process in Project Integration Management? |
|
Definition
1. Expertise 2. Data Gathering 3. Interpersonal and team skills 4. Meetings |
|
|
Term
What are the outputs for the 1st process in Project Integration Management? |
|
Definition
1. Project Charter 2. Assumptions log |
|
|
Term
What are the inputs for the 2nd process in Project Integration Management? |
|
Definition
1. Project Charter 2. Outputs from other processes 3. EEfs 4. OPAs |
|
|
Term
What are the Tools and Techniques for the 2nd process in Project Integration Management? |
|
Definition
1. Expertise 2. Data Gathering 3. Interpersonal and team skills 4. Meetings |
|
|
Term
What are the Outputs for the 2nd process in Project Integration Management? |
|
Definition
|
|
Term
What are the subsidiary components of the PMP? |
|
Definition
1. Scope Management Plan 2. Schedule Management Plan 3. Cost Management Plan 4. Communication Management Plan 5. Risk Management Plan 6. Resource Management Plan 7. Quality Management Plan 8. Procurement Management Plan 9. Stakeholder Management Plan 10. Requirements Management Plan 11. Change Management Plan 12. Configuration Management Plan 13. Scope Baseline 14. Schedule Baseline 15. Cost Baseline 16. Performance Measurement Baseline 17. Development Approach 18. Project Life Cycle Description |
|
|