Term
What are the inputs for the 2nd process in Project Procurement Management? |
|
Definition
1. PMP 2. Project Documents 3. Procurement Documentation (outputs from 1st process) 4. Seller Proposals 5. EEFs 6. OPAs |
|
|
Term
What are the tools and techniques of the 2nd process in Project Procurement Management? |
|
Definition
1. Expertise 2. Agreements 3. Change Requests 4. PMP Updates 5. PD Updates 6. OPA Updates |
|
|
Term
What are the outputs of the 2nd process in Project Procurement Management? |
|
Definition
1. Selected sellers 2. Agreements 3. Change Requests 4. PMP Updates 5. PD Updates 6. OPA Updates |
|
|
Term
What are the inputs for the third process in Project Procurement Management? |
|
Definition
1. PMP 2. PD 3. Agreements 4. Procurement Documentation 5. Approved Change Requests 6. WPD 7. EEFs 8. OPAs |
|
|
Term
What are the tools and techniques for the 3rd process in Project Procurement Management? |
|
Definition
1. Expertise 2. Claims Administration 3. Data Analysis 4. Inspections 5. Audits |
|
|
Term
What are the outputs for the 3rd process in Project Procurement Management? |
|
Definition
1. Closed procurements 2. WPI 3. Procurement Documentation Updates 4. Change Requests 5. PMP Updates 6. PD Updates 7. OPA Updates |
|
|